ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SOLADO DE 2" MEZCLA 1:12 CEMENTO
HORMIGON
RENDIMIENTO EN 8 HRS: 100 m2
APORTE: 12.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0160 18.14 0.29
OPERARIO hh 0.1600 15.12 2.42
OFICIAL hh 0.0800 13.14 1.05
PEON hh 0.6400 11.84 7.58
OPERADOR EQUIPO hh 0.0800 17.39 1.39
TOTAL 12.73
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
HORMIGON m3 0.6500 22.50 14.63
CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 0.1515 14.45 2.19
AGUA m3 0.0081 5.70 0.05
TOTAL 16.86
COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL
GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.0300 11.70 0.35
ACEITE MOTOR GASOLINA SAE 30W gal 0.0010 57.00 0.06
GRASA MULTIPLE EP lb 0.0020 5.65 0.01
TOTAL 0.42
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0800 30.50 30.50
HERRAMIENTA MANUAL % MO 0.0500 12.73 0.64
TOTAL 31.14
TOTAL P.U. 61.15
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO PREMEZCLADO F'c=100 Kg/cm2 PARA
CIMIENTOS
RENDIMIENTO EN 8 HRS: 25.00 m3
APORTE: 3.1250 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0320 18.14 0.58
OPERARIO hh 0.6400 15.12 9.68
OFICIAL hh 0.3200 13.14 4.20
PEON hh 1.2800 11.84 15.16
OPERADOR EQUIPO LIVIANO hh 0.3200 16.33 5.23
TOTAL 34.84
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CONCRETO PREMEZCLADO TIPO I F´C=100Kg/cm2 m3 1.0300 185.00 190.55
TOTAL 190.55
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.3200 5.53 1.77
HERRAMIENTA MANUAL % MO 0.0300 34.84 1.05
TOTAL 2.81
TOTAL P.U. 228.21
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ENCOF. Y DESENCOF. PARA SOBRECIMIENTOS
RENDIMIENTO EN 8 HRS: 16.00 m2
APORTE: 2.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0500 18.14 0.91
OPERARIO hh 0.5000 15.12 7.56
OFICIAL hh 0.5000 13.14 6.57
TOTAL 15.04
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE NEGRO RECOCIDO BWG N 8 KG 0.2600 2.96 0.77
CLAVO C/CABEZA P/CONSTRUCCION D. PROMEDIO KG 0.1600 3.02 0.48
MADERA TORNILLO p2 3.3500 5.40 18.09
TOTAL 19.34
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.0300 15.04 0.90
TOTAL 0.90
TOTAL P.U. 35.28
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO EN FALSOPISO MEZCLA 1:8 E=4"
RENDIMIENTO EN 8 HRS: 110 m2
APORTE: 13.7500 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0218 18.14 0.40
OPERARIO hh 0.2182 15.12 3.30
PEON hh 0.5818 11.84 6.89
OPERADOR EQUIPO hh 0.0727 17.39 1.26
TOTAL 11.85
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
HORMIGON m3 0.1450 22.50 3.26
REGLA DE MADERA p2 0.0600 5.20 0.31
AGUA m3 0.0160 5.70 0.09
TOTAL 3.67
COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL
GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.0273 11.70 0.32
ACEITE MOTOR GASOLINA SAE 30W gal 0.0009 57.00 0.05
GRASA MULTIPLE EP lb 0.0018 5.65 0.01
TOTAL 0.38
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0727 30.50 30.49
HERRAMIENTA MANUAL % MO 0.0300 11.85 4.89
TOTAL 35.38
TOTAL P.U. 51.27
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: EXCAVACION DE ZANJAS
RENDIMIENTO EN 8 HRS: 4.00 m3
APORTE: 0.5000 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.2000 18.14 3.63
OPERARIO hh 2.0000 15.12 30.24
TOTAL 33.87
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.0500 33.87 1.69
TOTAL 1.69
TOTAL P.U. 35.56
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CORTE MANUAL DE TERRENO
RENDIMIENTO EN 8 HRS: 40.00 m2
APORTE: 5.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.2000 18.14 3.63
OPERARIO hh 0.2000 15.12 3.02
TOTAL 6.65
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.0500 6.65 0.33
TOTAL 0.33
TOTAL P.U. 6.98
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ELIMINACION DESMONTE CON EQUIPO
RENDIMIENTO EN 8 HRS: 345.00 m3
APORTE: 43.1250 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0023 18.14 0.04
PEON hh 0.0464 11.84 0.55
TOTAL 0.59
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CAMION VOLQUETE 4 X 2 140-210 HP 6 M3 hm 0.0928 195.15 18.11
CARGADOR S/LLANTA 125 HP, 2.5 Y3 hm 0.0232 153.62 3.56
TOTAL 21.67
TOTAL P.U. 22.27
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: RELLENO CON MATERIAL PROPIO
RENDIMIENTO EN 8 HRS: 7.00 m3
APORTE: 0.8750 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.1143 18.14 2.07
PEON hh 1.1429 11.84 13.53
TOTAL 15.61
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.0500 15.61 0.78
TOTAL 0.78
TOTAL P.U. 16.39
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: TRAZO Y REPLANTEO
RENDIMIENTO EN 8 HRS: 300.00 m2
APORTE: 37.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0027 18.14 0.05
OPERARIO hh 0.0267 15.12 0.40
PEON hh 0.0533 11.84 0.63
TOTAL 1.08
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
YESO EN BOLSA DE 20 KG bls 0.0250 30.52 0.76
CLAVO C/CABEZA P/CONSTRUCCION D. PROMEDIO KG 0.0050 3.02 0.02
MADERA TORNILLO P2 0.0264 5.40 0.14
TOTAL 0.92
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CORDEL ROLLO DE 50m pza 0.0001 13.5 0.00
WINCHA DE 30m pza 0.0005 44.80 0.02
HERRAMIENTA MANUAL % MO 0.0300 1.08 0.03
TOTAL 0.06
TOTAL P.U. 2.06
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: TRAZO DE NIVELES Y REPLANTEO DURANTE EL
PROCESO
RENDIMIENTO EN 8 HRS: 300.00 m2
APORTE: 37.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0027 18.14 0.05
OPERARIO hh 0.0267 15.12 0.40
PEON hh 0.0533 11.84 0.63
TOTAL 1.08
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
YESO EN BOLSA DE 20 KG bls 0.0250 30.52 0.76
CLAVO C/CABEZA P/CONSTRUCCION D. PROMEDIO KG 0.0050 3.02 0.02
TOTAL 0.78
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CORDEL ROLLO DE 50m pza 0.0001 13.5 0.00
WINCHA DE 30m pza 0.0005 44.80 0.02
HERRAMIENTA MANUAL % MO 0.0300 1.08 0.03
TOTAL 0.06
TOTAL P.U. 1.92
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ZOCALO DE CERAMICO 20X20
RENDIMIENTO EN 8 HRS: 4.00 m2
APORTE: 0.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 0.660000 11.84 7.81
TOTAL 41.68
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ARENA GRUESA m3 0.025000 35.00 0.88
FRAGUA BLANCA kg 0.200000 8.00 1.60
CERAMICO 20x20 m2 1.050000 19.95 20.95
TOTAL 23.42
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.0500 41.68 2.08
TOTAL 2.08
TOTAL P.U. 67.19
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ZOCALO DE CEMENTO SIMPLE MEZCLA CEMENTO-
ARENA
RENDIMIENTO EN 8 HRS: 14.00 m2
APORTE: 1.7500 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.057100 18.14 1.04
OPERARIO hh 0.571400 15.12 8.64
PEON hh 0.382900 11.84 4.53
TOTAL 14.21
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ARENA FINA m3 0.021000 35.00 0.74
CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 0.186900 14.45 2.70
CLAVO C/CABEZA P/CONSTRUCCION DE PROMEDIO kg 0.030000 3.02 0.09
MADERA ANDAMIAJE p2 0.520000 5.40 2.81
AGUA m3 0.005600 5.70 0.03
TOTAL 6.37
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 14.21 0.43
TOTAL 0.43
TOTAL P.U. 21.00
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: PUERTA POSTERIOR CONTRAPLACADA DE 0.65 M DE
ANCHO
RENDIMIENTO EN 8 HRS: 3.00 m2
APORTE: 0.3750 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.666700 18.14 12.09
OPERARIO hh 2.666700 15.12 40.32
OFICIAL hh 2.666700 13.14 35.04
TOTAL 87.45
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.066900 3.02 0.20
MADERA CEDRO p2 10.290000 8.60 88.49
TRIPLAY LUPUNA 4X 8 X 6mm pza 1.000000 33.00 33.00
LIJA P/MADERA hja 1.100000 1.00 1.10
COLA SINTETICA gal 0.102800 22.70 2.33
TOTAL 125.13
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CEPILLADORA ELECTRICA hm 0.533300 4.29 6.86
SIERRA CIRCULAR hm 0.533300 3.91 0.78
HERRAMIENTA MANUAL % MO 0.030000 87.45 0.98
TOTAL 8.63
TOTAL P.U. 221.21
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: PUERTAS CONTRAPLACADAS DE 0.65 M DE ANCHO
RENDIMIENTO EN 8 HRS: 3.00 m2
APORTE: 0.3750 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.666700 18.14 12.09
OPERARIO hh 2.666700 15.12 40.32
OFICIAL hh 2.666700 13.14 35.04
TOTAL 87.45
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.066900 3.02 0.20
MADERA CEDRO p2 10.290000 8.60 88.49
TRIPLAY LUPUNA 4X 8 X 4mm pza 1.000000 21.75 21.75
LIJA P/MADERA hja 1.100000 1.00 1.10
COLA SINTETICA gal 0.102800 22.70 2.33
TOTAL 113.88
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CEPILLADORA ELECTRICA hm 0.533300 4.29 2.29
SIERRA CIRCULAR hm 0.533300 3.91 2.09
HERRAMIENTA MANUAL % MO 0.030000 87.45 2.62
TOTAL 7.00
TOTAL P.U. 208.33
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP
RENDIMIENTO EN 8 HRS: 25.00 pza
APORTE: 3.1250 h/pza
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.032000 18.14 0.58
OPERARIO hh 0.320000 15.12 4.84
OFICIAL hh 0.320000 13.14 4.20
TOTAL 9.62
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37
TUBO PVC AGUA S.P CLASE 10 ½" X 5m pza 0.210000 6.19 1.30
TOTAL 2.67
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 9.62 0.29
TOTAL 0.29
TOTAL P.U. 12.58
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA DE AGUA FRIA DE 1/2"
RENDIMIENTO EN 8 HRS: 3.00 Pto
APORTE: 0.3750 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.266700 18.14 4.84
OPERARIO hh 2.666700 15.12 40.32
OFICIAL hh 1.333333 13.14 17.52
TOTAL 62.68
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PEGAMENTO P/TUBO PVC gal 0.030000 139.92 4.20
TUBO PVC AGUA S.P CLASE 10 ½" X 5m pza 0.412000 6.19 2.55
CODO PVC AGUA DOBLE CAMPAÑA S.P. ½" X 90˚ pza 2.000000 0.96 1.92
TEE PVC AGUA S.P. ½" pza 1.000000 1.23 1.23
TOTAL 9.90
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 62.68 1.88
TOTAL 1.88
TOTAL P.U. 74.46
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: VALVULAS DE COMPUERTA DE BRONCE DE
1/2"
RENDIMIENTO EN 8 HRS: 6.00 pza
APORTE: 0.7500 h/pza
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.133300 18.14 2.42
OPERARIO hh 1.333300 15.12 20.16
OFICIAL hh 0.666700 13.14 8.76
TOTAL 31.34
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CINTA TEFLON pza 0.100000 1.16 0.12
UNION UNIVERSAL ACERO GALV. ½" pza 2.000000 7.64 15.28
NIPLE ACERO GALV. TIPO ISO -½" X 1¼" pza 2.000000 1.40 2.80
VALVULA COMPUERTA PESADA BRONCE 250 LB ½" pza 1.000000 22.76 22.76
TOTAL 40.96
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 31.34 0.71
TOTAL 0.71
TOTAL P.U. 73.00
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: RED DE DESAGUE DE 4" EN PVC
RENDIMIENTO EN 8 HRS: 20.00 m
APORTE: 2.5000 h/m
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.040000 18.14 0.73
OPERARIO hh 0.400000 15.12 6.05
PEON hh 0.800000 11.86 9.49
TOTAL 16.26
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37
TUBO PVC DESAGUE SAL 4" X 3m pza 0.350000 19.11 6.69
TOTAL 8.06
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 16.26 0.49
TOTAL 0.49
TOTAL P.U. 24.81
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: TUBERIA DE DESAGUE PVC SAL DE 2" PARA VENTILACION
RENDIMIENTO EN 8 HRS: 20.00 m
APORTE: 2.5000 h/m
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.040000 18.14 0.73
OPERARIO hh 0.400000 15.12 6.05
PEON hh 0.800000 11.86 9.49
TOTAL 16.26
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37
TUBO PVC DESAGUE SAL 2" X 3m pza 0.350000 7.48 2.62
TOTAL 3.99
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 16.26 0.49
TOTAL 0.49
TOTAL P.U. 20.74
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: RED DE DESAGUE DE 2" EN PVC
RENDIMIENTO EN 8 HRS: 20.00 m
APORTE: 2.5000 h/m
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.040000 18.14 0.73
OPERARIO hh 0.400000 15.12 6.05
PEON hh 0.800000 11.86 9.49
TOTAL 16.26
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37
TUBO PVC DESAGUE SAL 2" X 3m pza 0.350000 7.48 2.62
TOTAL 3.99
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 16.26 0.49
TOTAL 0.49
TOTAL P.U. 20.74
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA DE DESAGUE DE 4"
RENDIMIENTO EN 8 HRS: 4.00 pto
APORTE: 0.5000 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 2.000000 11.86 23.72
TOTAL 57.59
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PEGAMENTO P/TUBO PVC gal 0.030000 137.10 4.11
TUBO PVC DESAGUE SAL 4" X 3m pza 0.350000 19.11 6.69
CODO PVC DESAGUE SAL 4" X 90" pza 1.030000 5.33 5.49
TRAMPA P PVC DESAGUE SAL 4" pza 1.030000 34.21 35.24
YEE PVC DESAGUE SAL 4" pza 1.030000 8.61 8.87
TOTAL 60.40
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 57.59 1.73
TOTAL 1.73
TOTAL P.U. 119.71
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA DE DESAGUE DE 2"
RENDIMIENTO EN 8 HRS: 4.00 pto
APORTE: 0.5000 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 2.000000 11.86 23.72
TOTAL 57.59
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PEGAMENTO P/TUBO PVC gal 0.030000 137.10 4.11
TUBO PVC DESAGUE SAL 2" X 3m pza 0.350000 7.48 2.62
CODO PVC DESAGUE SAL 2" X 90" pza 1.030000 1.31 1.35
TRAMPA P PVC DESAGUE SAL 2" pza 1.030000 5.80 5.97
YEE PVC DESAGUE SAL 2" pza 1.030000 2.44 2.51
TOTAL 16.57
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 57.59 1.73
TOTAL 1.73
TOTAL P.U. 75.88
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CAJA DE REGISTRO DE ALBAÑILERIA DE 10" X
20"
RENDIMIENTO EN 8 HRS: 4.00 pza
APORTE: 0.5000 h/pza
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 2.000000 11.86 23.72
TOTAL 57.59
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ARENA FINA m3 0.030000 38.00 1.14
ARENA GRUESA m3 0.060000 35.00 2.10
PIEDRA CHANCADA DE ½" - ¾" HUSO 67 m3 0.250000 41.00 10.25
CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 1.500000 14.45 21.68
ACERO LISO GDO. 60 PRECIO PROM. P/Kg kg 10.000000 4.35 43.50
CLAVO C/CABEZA P/CONSTRUCCION DE PROMEDIO kg 0.860000 3.02 2.60
LADRILLO ARCILLA KING KONG 18 HUECOS mll 0.035000 571.43 20.00
AGUA m3 0.010000 5.70 0.06
TOTAL 101.32
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 57.59 1.73
TOTAL 1.73
TOTAL P.U. 160.63
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: REGISTRO ROSCADO DE BRONCE DE 2"
RENDIMIENTO EN 8 HRS: 8.00 pza
APORTE: 1.0000 h/pza
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.100000 18.14 1.81
OPERARIO hh 1.000000 15.12 15.12
TOTAL 16.93
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
REGISTRO ROSCADO DE BRONCE 2" pza 1.000000 8.55 8.55
CODO PVC DESAGUE SAL 2" X 90˚ pza 1.000000 3.18 3.18
TEE SANITARIA PVC DESAGUE SAL 2" pza 1.000000 12.68 12.68
TOTAL 24.41
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 16.93 0.51
TOTAL 0.51
TOTAL P.U. 30.12
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: REGISTRO ROSCADO DE BRONCE DE 4"
RENDIMIENTO EN 8 HRS: 6.00 pza
APORTE: 0.7500 h/pza
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.133300 18.14 2.42
OPERARIO hh 1.333300 15.12 20.16
PEON hh 0.666700 11.84 7.89
TOTAL 30.47
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
REGISTRO ROSCADO DE BRONCE CROMADO 4" pza 1.000000 26.14 26.14
CODO PVC DESAGUE SAL 4" X 90˚ pza 1.000000 5.30 5.30
TEE SANITARIA PVC DESAGUE SAL 4" pza 1.000000 11.84 11.84
TOTAL 43.28
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 30.47 0.91
TOTAL 0.91
TOTAL P.U. 74.67
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CENTRO DE LUZ
RENDIMIENTO EN 8 HRS: 5.00 pto
APORTE: 0.6250 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.160000 18.14 2.90
OPERARIO hh 1.600000 15.12 24.19
PEON hh 1.600000 11.84 18.94
TOTAL 46.04
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CABLE TW 12 AWG m 9.000000 1.29 11.61
CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 3.90 3.90
CINTA AISLANTE ELECTRICA pza 0.100000 2.45 0.25
TUBO PVC ELECTRICO SEL ¾" X 3M pza 1.500000 2.35 3.53
CONEXIÓN A CAJA PVC ELECTRICA SEL ¾" pza 1.000000 0.16 0.16
CURVA PVC ELECTRICA SEL ¾" X 45˚ pza 3.000000 0.54 1.62
UNION PVC ELECTRICA SEL ¾" pza 1.000000 0.27 0.27
TOTAL 21.33
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.050000 46.04 2.30
TOTAL 2.30
TOTAL P.U. 69.67
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA PARA BRAQUETES
RENDIMIENTO EN 8 HRS: 4.00 pza
APORTE: 0.5000 h/pza
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 1.000000 11.84 11.84
TOTAL 45.71
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ARTFAC. ALUMB. INTERIOR BRAQUETE ECONOMICO BE. 220 AF pza 1.000000 81.97 81.97
TOTAL 81.97
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 45.71 0.69
TOTAL 0.69
TOTAL P.U. 128.36
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA PARA TOMACORRIENTE BIPOLAR
DOBLE
RENDIMIENTO EN 8 HRS: 4.00 pto
APORTE: 0.5000 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 2.000000 11.84 23.68
TOTAL 57.55
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CABLE TW 12 AWG m 16.000000 1.29 20.64
TOMACORRIENTE DOBLE UNIVERSAL pza 1.050000 7.80 8.19
CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 1.050000 1.35 1.42
TUBO PVC ELECTRICO SEL ¾" X 3M pza 1.500000 4.89 7.34
CONEXIÓN A CAJA PVC ELECTRICA SEL ¾" pza 2.000000 0.37 0.74
CURVA PVC ELECTRICA SEL ¾" X 45˚ pza 3.000000 1.71 5.13
UNION PVC ELECTRICA SEL ¾" pza 1.000000 0.61 0.61
TOTAL 44.06
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.050000 57.55 1.44
TOTAL 1.44
TOTAL P.U. 103.05
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA DE TIMBRE
RENDIMIENTO EN 8 HRS: 2.00 pto
APORTE: 0.2500 h/pto
MANO DE OBRA UNIDA
D CANTIDA
D COST
O SUBTOTA
L
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 4.000000 15.12 60.48
PEON hh 2.000000 11.84 23.68
TOTAL 91.42
MATERIALES UNIDA
D CANTIDA
D COST
O SUBTOTA
L
CAJA DE PASE CUADRADA F.G. 100 X 100 X 40mm pza 1.000000 4.50 4.50
TUBO PVC ELECTRICO SAP ¾" X 3M pza 6.000000 4.89 29.34
CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 2.000000 0.37 0.74
CURVA PVC ELECTRICA SAP ¾" X 90˚ pza 2.000000 1.71 3.42
UNION PVC ELECTRICA SAP ¾" pza 2.000000 0.61 1.22
TOTAL 39.22
EQUIPOS UNIDA
D CANTIDA
D COST
O SUBTOTA
L
HERRAMIENTA MANUAL % MO 0.050000 91.42 1.14
TOTAL 1.14
TOTAL P.U. 131.78
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: TABLERO DE DISTRIBUCION 24 POLOS
RENDIMIENTO EN 8 HRS: 1.00 pza
APORTE: 0.1250 h/pza
MANO DE OBRA UNIDA
D CANTIDA
D COST
O SUBTOTA
L
CAPATAZ hh 8.000000 18.14 145.12
OPERARIO hh 8.000000 15.12 120.96
PEON hh 4.000000 11.84 47.36
TOTAL 313.44
MATERIALES UNIDA
D CANTIDA
D COST
O SUBTOTA
L
TABLEROS ELECTRICO GABINETE METAL BARRA BRONCE 24 POLOS - TRIFASICO
pza 1.000000
314.00 314.00
TOTAL 314.00
EQUIPOS UNIDA
D CANTIDA
D COST
O SUBTOTA
L
HERRAMIENTA MANUAL % MO
0.050000 313.4
4 15.67
TOTAL 15.67
TOTAL P.U. 643.11
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS
RENDIMIENTO EN 8 HRS: 11.00 m2
APORTE: 1.3750 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.110000 18.14 2.00
OPERARIO hh 1.090000 15.12 16.48
OFICIAL hh 1.310000 13.14 17.21
PEON hh 0.440000 11.84 5.21
TOTAL 40.90
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
MADERA TONILLO pza 6.710000 5.40 36.23
CLAVOS DE 3¨ kg 0.240000 3.02 0.72
ALAMBRE Nº 8 kg 0.210000 2.96 0.62
TOTAL 37.58
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 40.90 1.23
TOTAL 1.23
TOTAL P.U. 79.71
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO PREMEZCLADO F'c = 175 Kg/CM2
RENDIMIENTO EN 8 HRS: 100.00 m3
APORTE: 12.5000 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.081000 18.14 1.47
OPERARIO hh 0.320000 15.12 4.84
PEON hh 0.720000 13.14 9.46
OPERADOR DE EQUIPO LIVIANO hh 0.160000 17.39 2.78
TOTAL 18.55
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CONCRETO PREMEZCLADO F'c = 175 Kg/CM2 m3 1.000000 208.80 208.80
TOTAL 208.80
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
BOMBA hm 0.080000 412.8 33.02
VIBRADORES DE 2" hm 0.160000 5.53 0.88
HERRAMIENTA MANUAL % MO 0.030000 18.55 0.56
TOTAL 34.47
TOTAL P.U. 261.82
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ACARREO DE MATERIAL EXCEDENTE
RENDIMIENTO EN 8 HRS: 6.00 m3
APORTE: 0.7500 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.130000 18.14 2.36
PEON hh 1.330000 11.84 15.75
TOTAL 18.11
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 18.11 0.54
TOTAL 0.54
TOTAL P.U. 18.65
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ENCOFRADO Y DESENCOFRADO
RENDIMIENTO EN 8 HRS: 14.00 m2
APORTE: 1.7500 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.080000 18.14 1.45
OPERARIO hh 0.770000 15.12 11.64
OFICIAL hh 0.990000 13.14 13.01
PEON hh 0.990000 11.84 11.72
TOTAL 37.82
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
MADERA TONILLO p2 5.150000 5.40 27.81
CLAVOS DE 2 ½ kg 0.110000 3.02 0.33
ALAMBRE NEGRO Nº 16 kg 0.100000 2.96 0.30
TOTAL 28.44
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 37.82 1.13
TOTAL 1.13
TOTAL P.U. 67.40
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ENCOFRADO Y DESENCOF. NORMAL EN LOSAS MACIZAS
RENDIMIENTO EN 8 HRS: 17.00 m2
APORTE: 2.1250 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.070000 18.14 1.27
OPERARIO hh 0.670000 15.12 10.13
OFICIAL hh 0.850000 13.14 11.17
PEON hh 0.360000 11.84 4.26
TOTAL 26.83
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
MADERA TONILLO p2 5.930000 5.40 32.02
CLAVOS DE 2 ½ kg 0.140000 3.02 0.42
ALAMBRE NEGRO Nº 16 kg 0.100000 2.96 0.30
TOTAL 32.74
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 26.83 0.80
TOTAL 0.80
TOTAL P.U. 60.38
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 175 KG/CM2
RENDIMIENTO EN 8 HRS: 10.00 m3
APORTE: 1.2500 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.230000 18.14 4.17
OPERARIO hh 2.000000 15.12 30.24
OFICIAL hh 2.000000 13.14 26.28
PEON hh 10.270000 11.84 121.60
OPERADOR EQUIPO LIVIANO hh 3.000000 17.35 52.05
TOTAL 234.34
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 8.430000 14.45 121.81
ARENA GRUESA m3 0.540000 35.00 18.90
PIEDRA CHANCADA ½" m3 0.550000 41.00 22.55
TOTAL 163.26
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE 9-11 P3 hm 1.000000 30.5 30.50
VIBRADOR DE 2.0" 4HP hm 1.000000 5.53 5.53
WINCHE ELECTRICO hm 1.000000 5.53 5.53
HERRAMIENTA MANUAL % MO 0.030000 234.34 7.03
TOTAL 48.59
TOTAL P.U. 446.19
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO EN MUROS F'c=175 KG/m2 , CON 10 CM
RENDIMIENTO EN 8 HRS: 27.00 m3
APORTE: 3.3750 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.120000 18.14 2.18
OPERARIO hh 0.960000 15.12 14.52
OFICIAL hh 0.640000 13.14 8.41
PEON hh 3.680000 11.84 43.57
OPERADOR EQUIPO LIVIANO hh 0.960000 17.35 16.66
TOTAL 85.33
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 8.430000 14.45 121.81
ARENA GRUESA m3 0.540000 35.00 18.90
PIEDRA CHANCADA ½" m3 0.550000 41.00 22.55
TOTAL 163.26
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE 9-11 P3 hm 0.320000 30.5 9.76
VIBRADOR DE 2.0" 4HP hm 0.320000 5.53 1.77
WINCHE ELECTRICO DE 2 TAMBORES hm 0.320000 5.53 1.77
HERRAMIENTA MANUAL % MO 0.300000 85.33 25.60
TOTAL 38.90
TOTAL P.U. 287.49
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: MURO CON LADRILLO PANDERETA DE CUELLO
RENDIMIENTO EN 8 HRS: 9.00 m2
APORTE: 1.1250 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.112000 18.14 2.03
OPERARIO hh 1.120000 15.12 16.93
PEON hh 0.784000 11.84 9.28
TOTAL 28.25
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.124000 14.45 1.79
ARENA GRUESA m3 0.018000 35.00 0.63
CLAVOS DE 3" kg 0.022000 3.02 0.07
LADRILLO PANDERETA pz 30.000000 0.56 16.80
TOTAL 19.29
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
ANDAMIO DE MADERA P2 0.580000 5.4 3.13
HERRAMIENTA MANUAL % MO 0.030000 28.25 0.85
TOTAL 3.98
TOTAL P.U. 51.52
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: MURO DE LADRILLO PANDERETA DE SOGA
RENDIMIENTO EN 8 HRS: 12.00 m2
APORTE: 1.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.073000 18.14 1.32
OPERARIO hh 1.734000 15.12 26.22
PEON hh 0.631000 11.84 7.47
TOTAL 35.01
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.163000 14.45 2.36
ARENA GRUESA m3 0.023000 35.00 0.81
CLAVOS DE 3" kg 0.022000 3.02 0.07
LADRILLO PANDERETA pz 35.000000 0.56 19.60
TOTAL 22.83
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
ANDAMIO DE MADERA P2 0.580000 5.4 3.13
HERRAMIENTA MANUAL % MO 0.030000 35.01 1.05
TOTAL 4.18
TOTAL P.U. 62.02
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: TARRAJEO PRIMARIO O RAYADO
RENDIMIENTO EN 8 HRS: 17.00 m2
APORTE: 2.1250 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.057000 18.14 1.03
OPERARIO hh 0.571000 15.12 8.63
PEON hh 0.286000 11.84 3.39
TOTAL 13.05
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.117000 14.45 1.69
CLAVOS DE 3" kg 0.022000 3.02 0.07
ARENA FINA m3 0.016000 38.00 0.61
TOTAL 2.37
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
ANDAMIO DE MADERA P2 0.580000 5.4 3.13
REGLA DE MADERA P2 0.025000 5.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 13.05 0.39
TOTAL 3.65
TOTAL P.U. 19.07
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: TARRAJEO EN INTERIORES
RENDIMIENTO EN 8 HRS: 34.00 m2
APORTE: 4.2500 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.063000 18.14 1.14
OPERARIO hh 0.635000 15.12 9.60
PEON hh 0.278000 11.84 3.29
TOTAL 14.04
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.117000 14.45 1.69
CLAVOS DE 3" kg 0.022000 3.02 0.07
ARENA FINA m3 0.016000 38.00 0.61
TOTAL 2.37
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
ANDAMIO DE MADERA P2 0.580000 5.4 3.13
REGLA DE MADERA P2 0.025000 5.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 14.04 0.42
TOTAL 3.68
TOTAL P.U. 20.08
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONTRAZOCALO CEMENTO H = 20 cm PULIDO
RENDIMIENTO EN 8 HRS: 22.00 ml
APORTE: 2.7500 h/ml
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 0.400000 15.12 6.05
PEON hh 0.132000 11.84 1.56
TOTAL 14.87
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.031000 14.45 0.45
ARENA FINA m3 0.004000 38.00 0.15
TOTAL 0.60
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 14.87 0.45
TOTAL 0.45
TOTAL P.U. 15.91
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: COLOCACION INODORO
RENDIMIENTO EN 8 HRS: 4.00 pz
APORTE: 0.5000 h/pz
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 4.000000 15.12 60.48
PEON hh 2.000000 11.84 23.68
TOTAL 91.42
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74
TOTAL 2.74
TOTAL P.U. 94.16
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: RELLENO COMPACTADO CON MATERIAL DE PRESTAMO
RENDIMIENTO EN 8 HRS: 7.00 m3
APORTE: 0.8750 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.110000 18.14 2.00
PEON hh 1.140000 11.84 13.50
TOTAL 15.49
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
MATERIAL PARA RELLENO m3 1.300000 30.00 39.00
TOTAL 39.00
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 15.49 0.46
TOTAL 0.46
TOTAL P.U. 54.96
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: NIVELACION INTERIOR Y COMPACTACION
RENDIMIENTO EN 8 HRS: 120.00 m2
APORTE: 15.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.007000 18.14 0.13
OPERARIO hh 0.067000 15.12 1.01
PEON hh 0.067000 11.84 0.79
TOTAL 1.93
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CLAVOS DE 3" kg 0.010000 3.02 0.03
TOTAL 0.03
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
REGLA DE MADERA P2 0.030000 5.2 0.16
HERRAMIENTA MANUAL % MO 0.030000 1.93 0.06
TOTAL 0.21
TOTAL P.U. 2.18
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ACERO EN SOBRECIMIENTO REFORZADO GRADO 60
RENDIMIENTO EN 8 HRS: 280.00 kg
APORTE: 35.0000 h/kg
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.004000 18.14 0.07
OPERARIO hh 0.032000 15.12 0.48
OFICIAL hh 0.032000 13.14 0.42
TOTAL 0.98
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18
FIERRO CORRUGADO kg 1.070000 3.50 3.75
TOTAL 3.92
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CIZALLA hm 0.032000 4.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03
TOTAL 0.16
TOTAL P.U. 5.06
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS
RENDIMIENTO EN 8 HRS: 280.00 kg
APORTE: 35.0000 h/kg
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.004000 18.14 0.07
OPERARIO hh 0.032000 15.12 0.48
OFICIAL hh 0.032000 13.14 0.42
TOTAL 0.98
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18
FIERRO CORRUGADO kg 1.070000 3.50 3.75
TOTAL 3.92
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CIZALLA hm 0.032000 4.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03
TOTAL 0.16
TOTAL P.U. 5.06
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ACERO GRADO 60 EN VIGAS
RENDIMIENTO EN 8 HRS: 280.00 kg
APORTE: 35.0000 h/kg
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.004000 18.14 0.07
OPERARIO hh 0.032000 15.12 0.48
OFICIAL hh 0.032000 13.14 0.42
TOTAL 0.98
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18
FIERRO CORRUGADO kg 1.070000 3.50 3.75
TOTAL 3.92
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CIZALLA hm 0.032000 4.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03
TOTAL 0.16
TOTAL P.U. 5.06
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ACERO GRADO 60 EN LOSAS ALIGERADAS
RENDIMIENTO EN 8 HRS: 280.00 kg
APORTE: 35.0000 h/kg
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.004000 18.14 0.07
OPERARIO hh 0.032000 15.12 0.48
OFICIAL hh 0.032000 13.14 0.42
TOTAL 0.98
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18
FIERRO CORRUGADO kg 1.070000 3.50 3.75
TOTAL 3.92
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CIZALLA hm 0.032000 4.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03
TOTAL 0.16
TOTAL P.U. 5.06
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ACERO GRADO 60 EN LOSAS MACIZAS
RENDIMIENTO EN 8 HRS: 280.00 kg
APORTE: 35.0000 h/kg
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.004000 18.14 0.07
OPERARIO hh 0.032000 15.12 0.48
OFICIAL hh 0.032000 13.14 0.42
TOTAL 0.98
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18
FIERRO CORRUGADO kg 1.070000 3.50 3.75
TOTAL 3.92
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CIZALLA hm 0.032000 4.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03
TOTAL 0.16
TOTAL P.U. 5.06
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ACERO EN MURO DE ALBANILERIA ARMADA
RENDIMIENTO EN 8 HRS: 280.00 kg
APORTE: 35.0000 h/kg
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.004000 18.14 0.07
OPERARIO hh 0.032000 15.12 0.48
OFICIAL hh 0.032000 13.14 0.42
TOTAL 0.98
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18
FIERRO CORRUGADO kg 1.070000 3.50 3.75
TOTAL 3.92
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CIZALLA hm 0.032000 4.2 0.13
HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03
TOTAL 0.16
TOTAL P.U. 5.06
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: ENCOF. Y DESENCOF. EN MUROS TABIQUES Y PLACAS
RENDIMIENTO EN 8 HRS: 12.00 m2
APORTE: 1.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.100000 18.14 1.81
OPERARIO hh 1.000000 15.12 15.12
OFICIAL hh 1.200000 13.14 15.77
PEON hh 0.400000 11.84 4.74
TOTAL 37.44
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
MADERA TORNILLO P2 5.160000 5.4 27.86
ALAMBRE NEGRO Nº 8 kg 0.300000 2.96 0.89
CLAVO 3" kg 0.170000 3.02 0.51
TOTAL 29.27
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 37.44 1.12
TOTAL 1.12
TOTAL P.U. 67.83
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: MURO DE LADRILLO DE SOGA KING KONG
RENDIMIENTO EN 8 HRS: 12.00 m2
APORTE: 1.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.085000 18.14 1.54
OPERARIO hh 0.846000 15.12 12.79
PEON hh 0.719000 11.84 8.51
TOTAL 22.85
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.218000 14.45 3.15
ARENA GRUESA m3 0.031000 35.00 1.09
CLAVOS DE 3" kg 0.022000 3.02 0.07
LADRILLO KIN KONG 18 HUECOS mll 0.050000 571.43 28.57
TOTAL 32.87
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
ANDAMIO DE MADERA P2 0.580000 5.4 3.13
HERRAMIENTA MANUAL % MO 0.030000 22.85 0.69
TOTAL 3.82
TOTAL P.U. 59.54
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: FALSO CIMIENTO
RENDIMIENTO EN 8 HRS: 25.00 m3
APORTE: 3.1250 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0640 18.14 1.16
OPERARIO hh 0.6400 15.12 9.68
OFICIAL hh 0.3200 13.14 4.20
PEON hh 2.5600 11.84 30.31
OPERADOR EQUIPO hh 0.3200 17.35 5.55
TOTAL 50.90
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
PIEDRA GRANDE m3 0.5200 30.00 15.60
HORMIGON m3 0.7800 22.50 17.55
AGUA m3 0.1620 5.70 0.92
CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 2.9000 14.45 41.91
TOTAL 75.98
COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL
GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.1200 11.70 1.40
ACEITE MOTOR GASOLINA SAE 30W gal 0.0040 57.00 0.23
GRASA MULTIPLE EP lb 0.0080 5.80 0.05
TOTAL 1.68
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.3200 30.5 9.76
HERRAMIENTA MANUAL % MO 0.030000 50.90 1.53
TOTAL 11.29
TOTAL P.U. 139.85
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO PREMEZCLADO F'c=100
SOBRECIMIENTOS
RENDIMIENTO EN 8 HRS: 60.00 m3
APORTE: 7.5000 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0133 18.14 0.24
OPERARIO hh 0.2667 15.12 4.03
OFICIAL hh 0.1333 13.14 1.75
PEON hh 0.5333 11.84 6.31
OPERADOR EQUIPO LIVIANO hh 0.1333 17.35 2.31
TOTAL 14.65
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CONCRETO PREMEZCLADO TIPO I F´C=100Kg/cm2 m3 1.0300 185.00 190.55
TOTAL 190.55
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.1333 5.38 0.72
HERRAMIENTA MANUAL % MO 0.0300 14.65 0.44
TOTAL 1.16
TOTAL P.U. 206.36
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO PARA VIGAS DE F'c= 280 KG/m2
RENDIMIENTO EN 8 HRS: 25.00 m3
APORTE: 3.1250 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0640 18.14 1.16
OPERARIO hh 0.6400 15.12 9.68
OFICIAL hh 0.3200 13.14 4.20
PEON hh 2.5600 11.84 30.31
OPERADOR EQUIPO hh 0.6400 17.35 11.10
TOTAL 56.46
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ARENA GRUESA m3 0.5000 35 17.50
PIEDRA CHANCADA DE ½" - ¾" HUSO 67 m3 0.8000 41 32.80
CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 8.4000 14.45 121.38
AGUA m3 0.1800 0.00
TOTAL 171.68
COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL
GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.1200 11.70 1.40
ACEITE MOTOR GASOLINA SAE 30W gal 0.0040 57.00 0.23
GRASA MULTIPLE EP lb 0.0080 5.80 0.05
TOTAL 1.68
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.3200 30.5 9.76
VIBRADOR DE CONCRETO 4HP 2.40 plg hm 0.3200 5.38 1.72
HERRAMIENTA MANUAL % MO 0.0500 56.46 2.82
TOTAL 14.30
TOTAL P.U. 244.12
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO PREMEZCLADO F'c = 175 Kg/CM2
RENDIMIENTO EN 8 HRS: 60.00 m3
APORTE: 7.5000 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0133 18.14 0.24
OPERARIO hh 0.2667 15.12 4.03
OFICIAL hh 0.1333 13.14 1.75
PEON hh 0.5333 11.84 6.31
OPERADOR EQUIPO LIVIANO hh 0.1333 17.35 2.31
TOTAL 14.65
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CONCRETO PREMEZCLADO TIPO I F´C=175Kg/cm2 m3 1.0200 208.8 212.98
TOTAL 212.98
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.1333 5.38 0.72
HERRAMIENTA MANUAL % MO 0.0300 14.65 0.44
TOTAL 1.16
TOTAL P.U. 228.79
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO PREMEZCLADO F'C=175 kg/cm2 LOSA
MASIZA
RENDIMIENTO EN 8 HRS: 100.00 m3
APORTE: 12.5000 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0133 18.14 0.24
OPERARIO hh 0.2667 15.12 4.03
OFICIAL hh 0.1333 13.14 1.75
PEON hh 0.5333 11.84 6.31
OPERADOR EQUIPO LIVIANO hh 0.1333 17.35 2.31
TOTAL 14.65
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CONCRETO PREMEZCLADO TIPO I F´C=175Kg/cm2 m3 1.0200 208.8 212.98
TOTAL 212.98
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.1333 5.38 0.72
HERRAMIENTA MANUAL % MO 0.0300 14.65 0.44
TOTAL 1.16
TOTAL P.U. 228.79
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: COLOCACION LAVATORIO DE PARED BLANCO
RENDIMIENTO EN 8 HRS: 4.00 pz
APORTE: 0.5000 h/pz
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 4.000000 15.12 60.48
PEON hh 2.000000 11.84 23.68
TOTAL 91.42
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74
TOTAL 2.74
TOTAL P.U. 94.16
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: COLOCACION DE LAVADERO DE ACERO INOXIDABLE
RENDIMIENTO EN 8 HRS: 4.00 pz
APORTE: 0.5000 h/pz
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 4.000000 15.12 60.48
PEON hh 2.000000 11.84 23.68
TOTAL 91.42
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74
TOTAL 2.74
TOTAL P.U. 94.16
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: COLOCACION LAVADERO DE GRANITO
RENDIMIENTO EN 8 HRS: 4.00 pz
APORTE: 0.5000 h/pz
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 4.000000 15.12 60.48
PEON hh 2.000000 11.84 23.68
TOTAL 91.42
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74
TOTAL 2.74
TOTAL P.U. 94.16
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: COLOCACION DUCHA SIMPLE
RENDIMIENTO EN 8 HRS: 4.00 pz
APORTE: 0.5000 h/pz
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 4.000000 15.12 60.48
PEON hh 2.000000 11.84 23.68
TOTAL 91.42
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74
TOTAL 2.74
TOTAL P.U. 94.16
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONTRAPISO DE 50 mm
RENDIMIENTO EN 8 HRS: 80.00 m2
APORTE: 10.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.030000 18.14 0.54
OPERARIO hh 0.300000 15.12 4.54
OFICIAL hh 0.100000 13.14 1.31
PEON hh 0.600000 11.84 7.10
OPERADOR EQUIPO LIVIANO hh 0.1000 17.35 1.74
TOTAL 15.23
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.1000 30.5 3.05
REGLA DE MADERA P2 0.060000 5.2 0.31
HERRAMIENTA MANUAL % MO 0.030000 15.23 0.46
TOTAL 3.82
TOTAL P.U. 19.05
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONTRAPISO DE 35 mm
RENDIMIENTO EN 8 HRS: 100.00 m2
APORTE: 12.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.024000 18.14 0.44
OPERARIO hh 0.240000 15.12 3.63
OFICIAL hh 0.080000 13.14 1.05
PEON hh 0.480000 11.84 5.68
OPERADOR EQUIPO LIVIANO hh 0.0800 17.35 1.39
TOTAL 12.19
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0800 30.5 2.44
REGLA DE MADERA P2 0.060000 5.2 0.31
HERRAMIENTA MANUAL % MO 0.030000 12.19 0.37
TOTAL 3.12
TOTAL P.U. 15.30
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: PISO DE CEMENTO PULIDO Y BRUÑADO
RENDIMIENTO EN 8 HRS: 120.00 m2
APORTE: 15.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.032000 18.14 0.58
OPERARIO hh 0.280000 15.12 4.23
OFICIAL hh 0.670000 13.14 8.80
PEON hh 0.520000 11.84 6.16
OPERADOR EQUIPO LIVIANO hh 0.0670 17.35 1.16
TOTAL 20.94
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.450000 14.45 6.50
ARENA GRUESA m3 0.021000 35.00 0.74
PIEDRA CHANCADA ½" m3 0.027000 41.00 1.11
ARENA FINA m3 0.009000 38.00 0.34
TOTAL 8.69
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0670 30.5 2.04
REGLA DE MADERA P2 0.099000 5.2 0.51
HERRAMIENTA MANUAL % MO 0.030000 20.94 0.63
TOTAL 3.19
TOTAL P.U. 32.81
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: PISO DE CERAMICO 20 x 20
RENDIMIENTO EN 8 HRS: 12.00 m2
APORTE: 1.5000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.089000 18.14 1.61
OPERARIO hh 0.088900 15.12 1.34
PEON hh 0.444000 11.84 5.26
TOTAL 8.22
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CEMENTO PORTLAND TIPO I bls 0.262000 14.45 3.79
CERAMICO 20 X 20 m2 1.050000 16.00 16.80
ARENA FINA m3 0.027000 38.00 1.03
TOTAL 21.61
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
REGLA DE MADERA P2 0.055000 5.2 0.29
HERRAMIENTA MANUAL % MO 0.030000 8.22 0.25
TOTAL 0.53
TOTAL P.U. 30.36
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: BRUÑAS EN MUROS
RENDIMIENTO EN 8 HRS: 25.00 ml
APORTE: 3.1250 h/ml
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.030000 18.14 0.54
OPERARIO hh 0.320000 15.12 4.84
PEON hh 0.110000 11.84 1.30
TOTAL 6.69
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 6.69 0.20
TOTAL 0.20
TOTAL P.U. 6.89
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: PUERTA PRINCIPAL DE CEDRO DE 0.80 M DE
ANCHO
RENDIMIENTO EN 8 HRS: 32.00 m²
APORTE: 4.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.400000 18.14 7.26
OPERARIO hh 4.000000 15.12 60.48
OFICIAL hh 4.000000 13.14 52.56
TOTAL 120.30
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.075000 3.02 0.23
MADERA CEDRO p2 17.000000 5.40 91.80
LIJA P/MADERA hja 1.100000 1.00 1.10
COLA SINTETICA gal 0.120000 22.70 2.72
TOTAL 95.85
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CEPILLADORA hm 0.800000 4.29 3.43
SIERRA CIRCULAR hm 0.800000 3.91 3.13
HERRAMIENTA MANUAL % MO 0.050000 120.30 6.01
TOTAL 12.57
TOTAL P.U. 228.72
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: PUERTA CORREDIZA DE 1.80 X 1.80 M
RENDIMIENTO EN 8 HRS: 32.00 m²
APORTE: 4.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.800000 18.14 14.51
OPERARIO hh 4.000000 15.12 60.48
OFICIAL hh 2.000000 13.14 26.28
TOTAL 101.27
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.075000 3.02 0.23
MADERA CEDRO p2 25.400000 5.40 137.16
LIJA P/MADERA hja 1.100000 1.00 1.10
COLA SINTETICA gal 0.120000 22.70 2.72
TOTAL 141.21
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
CEPILLADORA ELECTRICA hm 0.800000 4.29 3.43
SIERRA CIRCULAR hm 0.800000 3.91 3.13
HERRAMIENTA MANUAL % MO 0.030000 101.27 3.04
TOTAL 9.60
TOTAL P.U. 252.08
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA DE INTERRUPTOR SIMPLE
RENDIMIENTO EN 8 HRS: 4.00 pto
APORTE: 0.5000 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 2.000000 11.84 23.68
TOTAL 57.55
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE TW 12 AWG m 8.000000 1.23 9.84
INTERRUPTOR SIMPLE pza 1.050000 5.40 5.67
CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 1.050000 1.35 1.42
CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 1.60 1.60
CINTA AISLANTE ELECTRICA pza 0.100000 2.50 0.25
TUBO PVC ELECTRICO SAP ¾" X 3M pza 1.500000 4.89 7.34
CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 1.000000 0.37 0.37
CURVA PVC ELECTRICA SAP ¾" X 45˚ pza 2.000000 1.71 3.42
UNION PVC ELECTRICA SAP ¾" pza 1.000000 0.61 0.61
TOTAL 30.51
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 57.55 1.73
TOTAL 1.73
TOTAL P.U. 89.79
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA DE INTERRUPTOR DOBLE
RENDIMIENTO EN 8 HRS: 4.00 pto
APORTE: 0.5000 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 2.000000 11.84 23.68
TOTAL 57.55
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE TW 12 AWG m 16.000000 1.23 19.68
INTERRUPTOR DOBLE pza 1.050000 5.40 5.67
CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 1.050000 1.35 1.42
CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 1.60 1.60
CINTA AISLANTE ELECTRICA pza 0.100000 2.50 0.25
TUBO PVC ELECTRICO SAP ¾" X 3M pza 1.500000 4.89 7.34
CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 2.000000 0.37 0.74
CURVA PVC ELECTRICA SAP ¾" X 45˚ pza 2.000000 1.71 3.42
UNION PVC ELECTRICA SAP ¾" pza 1.000000 0.61 0.61
TOTAL 40.72
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 57.55 1.73
TOTAL 1.73
TOTAL P.U. 100.00
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: SALIDA DE INTERRUPTOR DE CONMUTACION
RENDIMIENTO EN 8 HRS: 4.00 pto
APORTE: 0.5000 h/pto
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.200000 18.14 3.63
OPERARIO hh 2.000000 15.12 30.24
PEON hh 2.000000 11.84 23.68
TOTAL 57.55
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
ALAMBRE TW 12 AWG m 16.000000 1.23 19.68
INTERRUPTOR CONMUTACION pza 2.050000 5.40 11.07
CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 2.050000 1.35 2.77
CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 1.60 1.60
CINTA AISLANTE ELECTRICA pza 0.100000 2.50 0.25
TUBO PVC ELECTRICO SAP ¾" X 3M pza 1.500000 4.89 7.34
CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 2.000000 0.37 0.74
CURVA PVC ELECTRICA SAP ¾" X 45˚ pza 3.000000 1.71 5.13
UNION PVC ELECTRICA SAP ¾" pza 1.000000 0.61 0.61
TOTAL 49.18
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 57.55 1.73
TOTAL 1.73
TOTAL P.U. 108.46
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: LIMPIEZA GENERAL DE OBRA
RENDIMIENTO EN 8 HRS: 40.00 m2
APORTE: 5.0000 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
OPERARIO hh 0.020000 15.12 0.30
PEON hh 0.200000 11.84 2.37
TOTAL 2.67
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.050000 2.67 0.13
TOTAL 0.13
TOTAL P.U. 2.80
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: CONCRETO LIQUIDO PREMEZCLADO EN MUROS
RENDIMIENTO EN 8 HRS: 8.00 m3
APORTE: 1.0000 h/m3
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.0133 18.14 0.24
OPERARIO hh 0.2667 15.12 4.03
OFICIAL hh 0.1333 13.14 1.75
PEON hh 0.5333 11.84 6.31
TOTAL 12.34
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
CONCRETO LIQUIDO PREMEZCLADO m3 1.0200 250.73 255.74
TOTAL 255.74
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.0300 12.34 0.37
TOTAL 0.37
TOTAL P.U. 268.45
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: VENTANA PRINCIPAL DE 1.80 X 0.90 M DE 2
HOJAS
RENDIMIENTO EN 8 HRS: 2.50 m²
APORTE: 0.3125 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
OPERARIO hh 3.200000 15.12 48.38
PEON hh 3.200000 11.84 37.89
TOTAL 86.27
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58
ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00
TOTAL 67.58
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
EQUIPO DE SOLDAR hm 3.200000 4.50 14.40
HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31
TOTAL 18.71
TOTAL P.U. 172.57
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: VENTANA POSTERIOR DE 1.20 X 0.90 M DE 2
HOJAS
RENDIMIENTO EN 8 HRS: 2.50 m²
APORTE: 0.3125 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
OPERARIO hh 3.200000 15.12 48.38
PEON hh 3.200000 11.84 37.89
TOTAL 86.27
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58
ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00
TOTAL 66.00
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
EQUIPO DE SOLDAR hm 3.200000 4.50 14.40
HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31
TOTAL 4.31
TOTAL P.U. 156.59
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: VENTANAS EN DORMITORIOS DE 1.50 X .90 M DE 2
HOJAS
RENDIMIENTO EN 8 HRS: 2.50 m²
APORTE: 0.3125 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
OPERARIO hh 3.200000 15.12 48.38
PEON hh 3.200000 11.84 37.89
TOTAL 86.27
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58
ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00
TOTAL 66.00
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
EQUIPO DE SOLDAR hm 3.200000 4.50 14.40
HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31
TOTAL 4.31
TOTAL P.U. 156.59
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: VENTANA CORREDIZA DE 1.55 X .90 M DE 2 HOJAS
RENDIMIENTO EN 8 HRS: 2.50 m²
APORTE: 0.3125 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
OPERARIO hh 3.200000 15.12 48.38
PEON hh 3.200000 11.84 37.89
TOTAL 86.27
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58
ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00
TOTAL 66.00
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
EQUIPO DE SOLDAR hm 3.200000 4.50 14.40
HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31
TOTAL 4.31
TOTAL P.U. 156.59
ANALISIS DE COSTO UNITARIO
PROYECTO: EXAMEN PARCIAL
DESCRIPCION: MURO DE LADRILLO SILICO CALCAREO
RENDIMIENTO EN 8 HRS: 7.50 m2
APORTE: 0.9375 h/m2
MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL
CAPATAZ hh 0.085000 18.14 1.54
OPERARIO hh 0.846000 15.12 12.79
PEON hh 0.719000 11.84 8.51
TOTAL 22.85
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
LADRILLO SILICO CALCAREO m2 1.030000 48.42 49.87
TOTAL 49.87
EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL
HERRAMIENTA MANUAL % MO 0.030000 22.85 0.69
TOTAL 0.69
TOTAL P.U. 73.40