CATALOGO DE CONCEPTOS
CLAVE CONCEPTO UNIDAD CANTIDAD
CONSTRUCCION DE EDIFICIOPRELIMINARES
1.1 TRAZO Y NIVELACION CON EQUIPO TOPOGRAFICO M2 350.001.2 RELLENO CON TEPETATE COMPACTADO AL 90% PROCTOR CO M3 2,000.001.3 EXCAVACION EN CEPA PARA DESPALNTE DE CIMENTACION C M3 3,000.00
ALBAÑILERIA Y ESTRUCTURA2.1 PZA 39.002.2 MURO DE BLOCK DE 20 CMS DE ESPESOR, C/MORTERO CEM-A M2 1,800.002.3 SUM. Y COLOC. PLACA DE ACERO 20x20 CMS 4 BARRENOS, I PZA 100.00
ACABADOS3.1 MURO DE TABLAROCA A 2 CARAS DE 9 CMS DE ESP. M2 1,800.003.2 PISO DE LOSETA DE CERAMICA DE 33x33 MARCA INTERCERA M2 1,500.003.3 PINTURA VINILICA EN MUROS MARCO COMEX TIPO VINIMEX M2 5,000.00
INSTALACIONES4.1 SUM. E INST. TUBO CONDUIT PARED GRUESA 19 MM M 45.004.2 SUM. E INST. CABLE THW CAL. 10 M 17.00
FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO1.3035Ó UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %)30.35%
(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES
CONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO ( 8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADA CON VARILLA DEL No. 3 (3/8"), A CADA 15 CMS DE SEPARACION EN AMBOS SENTIDOS Y 2 LECHOS; EL PRECIO INCLUYE: CONSTRUCCION DE DADO DE CIMENTACION DE 0.50 MTS x 0.50 MTS DE SECCION Y 1.60 MTS DE ALTURA, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADO CON 8 VARILLAS DEL No. 6 (3/4") Y ESTRIBOS DE VARILLA DEL No. 3 (3/8") A CADA 12 CMS; ACARREO DE TODOS LOS MATERIALES NECESARIOS PARA SU EJECUCION A CUALQUIER DISTANCIA; RETIRO Y LIMPIEZA DE SOBRANTES AL FINALIZAR LA ACTIVIDAD; ARMADO, CIMBRADO COMUN CON MADERA DE PINO DE 3RA, ACARREOS Y COLADO DE CONCRETO, VIBRADO CON EQUIPO (VIBRADOR PARA CONCRETO DE 5.5 HP), DESCIMBRADO Y CURADO CON MEMBRANA; MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION; P. U. O. T.
IMPORTE A PRECIO UNITARIO
$11.15 $3,902.50 $14.53 $5,085.50$433.56 $867,120.00 $565.14 $1,130,283.55$35.00 $105,000.00 $45.62 $136,866.61
$5,475.82 $213,556.92 $7,137.68 $278,369.63$325.00 $585,000.00 $423.63 $762,542.53$140.31 $14,031.00 $182.89 $18,289.29
$280.94 $505,692.00 $366.20 $659,165.22$450.00 $675,000.00 $586.57 $879,856.76$45.00 $225,000.00 $58.66 $293,285.59
$4,500.00 $202,500.00 $5,865.71 $263,957.03$9,000.00 $153,000.00 $11,731.42 $199,434.20TOTALES $3,549,802.42 1.3035 $4,627,135.91
PRESUPUESTO TOTAL SIN IVA $4,627,135.91% DE IVA (16%) $740,341.75
PRESUPUESTO TOTAL CON IVA $5,367,477.66
COSTO DIRECTO $3,549,802.42% DE INDIRECTOS 17.4934% $620,981.14
Ó UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %) SUBTOTAL 1 $4,170,783.56% DE FINANCIAMIENTO 0.3543% $14,777.09
SUBTOTAL 2 $4,185,560.64% DE UTILIDAD 10.0000% $418,556.06
SUBTOTAL 3 $4,604,116.71(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES 0.5000% $23,020.58
PRECIO UNITARIO $4,627,137.29
COSTO DIRECTO
IMPORTE A COSTO DIRECTO
PRECIO UNITARIO
GENERALIDADES : ART. 185 AL 188
CATALOGO DE CONCEPTOS
CLAVE CONCEPTO UNIDAD CANTIDAD
CONSTRUCCION DE CASA HABITACIONPRELIMINARES
1.1 TRAZO Y NIVELACION CO M2 350.00 $11.15
1.2 RELLENO CON TEPETATE M3 2,000.00 $433.56
1.3 EXCAVACION EN CEPA PAR M3 3,000.00 $35.00
ALBAÑILERIA Y ESTRUCTURA2.1 PZA 39.00 $5,475.82
2.2 MURO DE BLOCK DE 20 CM M2 1,800.00 $325.00
2.3 SUM. Y COLOC. PLACA DE PZA 100.00 $140.31
ACABADOS3.1 MURO DE TABLAROCA A 2 M2 1,800.00 $280.94
3.2 PISO DE LOSETA DE CERA M2 1,500.00 $450.00
3.3 PINTURA VINILICA EN MU M2 5,000.00 $45.00
INSTALACIONES4.1 SUM. E INST. TUBO COND M 45.00 $4,500.00
4.2 SUM. E INST. CABLE THW C M 17.00 $9,000.00
TOTALES
FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO1.3035 % DE INDIRECTOSÓ UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de30.35% % DE FINANCIAMIENTO
COSTO DIRECTO
CONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO ( 8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADA CON VARILLA DEL No. 3 (3/8"), A CADA 15 CMS DE SEPARACION EN AMBOS SENTIDOS Y 2 LECHOS; EL PRECIO INCLUYE: CONSTRUCCION DE DADO DE CIMENTACION DE 0.50 MTS x 0.50 MTS DE SECCION Y 1.60 MTS DE ALTURA, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADO CON 8 VARILLAS DEL No. 6 (3/4") Y ESTRIBOS DE VARILLA DEL No. 3 (3/8") A CADA 12 CMS; ACARREO DE TODOS LOS MATERIALES NECESARIOS PARA SU EJECUCION A CUALQUIER DISTANCIA; RETIRO Y LIMPIEZA DE SOBRANTES AL FINALIZAR LA ACTIVIDAD; ARMADO, CIMBRADO COMUN CON MADERA DE PINO DE 3RA, ACARREOS Y COLADO DE CONCRETO, VIBRADO CON EQUIPO (VIBRADOR PARA CONCRETO DE 5.5 HP), DESCIMBRADO Y CURADO CON MEMBRANA; MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION; P. U. O. T.
(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALESPRECIO UNITARIO
MES 1 MES 2
$3,902.50 $14.53 $5,086.88 100.00%$5,086.88
$867,120.00 $565.14 $1,130,283.55 30.00% 70.00%$339,085.07 $791,198.49
$105,000.00 $45.62 $136,866.61 100.00%$136,866.61
$213,556.92 $7,137.68 $278,369.63 70.00% 30.00%$194,858.74 $83,510.89
$585,000.00 $423.63 $762,542.53 20.00%$152,508.51
$14,031.00 $182.89 $18,289.29 100.00%$18,289.29
$505,692.00 $366.20 $659,165.22
$675,000.00 $586.57 $879,856.76
$225,000.00 $58.66 $293,285.59
$202,500.00 $5,865.71 $263,957.03
$153,000.00 $11,731.42 $199,434.20
$3,549,802.42 1.3035 $4,627,137.29
IMPORTE POR PERIODO $675,897.29 $1,045,507.17
IMPORTE ACUMULADO POR PERIODO $675,897.29 $1,721,404.46% POR PERIODO 14.61% 22.60%
% ACUMULADO POR PERIODO 14.61% 37.20%
COSTO DIRECTO $3,549,802.42% DE INDIRECTOS 17.4934% $620,981.14
SUBTOTAL 1 $4,170,783.56% DE FINANCIAMIENTO 0.3543% $14,777.09
SUBTOTAL 2 $4,185,560.64% DE UTILIDAD 10.0000% $418,556.06
SUBTOTAL 3 $4,604,116.71
IMPORTE A COSTO DIRECTO
PRECIO UNITARIO
IMPORTE A PRECIO UNITARIO
(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES 0.5000% $23,020.58PRECIO UNITARIO $4,627,137.29
MES 3 MES 4 MES 5 TOTAL
100.00%$5,086.88100.00%
$1,130,283.55100.00%
$136,866.61
100.00%$278,369.63
80.00% 100.00%$610,034.02 $762,542.53
100.00%$18,289.29
70.00% 30.00% 100.00%$461,415.66 $197,749.57 $659,165.22
60.00% 40.00% 100.00%$527,914.06 $351,942.71 $879,856.76
100.00% 100.00%$293,285.59 $293,285.59
50.00% 50.00% 100.00%$131,978.51 $131,978.51 $263,957.0350.00% 50.00% 100.00%
$99,717.10 $99,717.10 $199,434.20
$1,303,145.30 $957,359.24 $645,228.29
$3,024,549.75 $3,981,908.99 $4,627,137.2928.16% 20.69% 13.94%65.37% 86.06% 100.00%
Row 35
Row 33
Row 35
Row 33
ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO
CLAVE2.1
CLAVE
MAVAR3MAVAR6MAALARMAPOLMABARMADUEMACLAMADIEMACUR
MO1A1AAMO1F1AFMO1C1AC
EQVIB
HEREQS
MACON250
FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO1.3035Ó UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %)30.35%
CONSIDERANDO PAGO DE ESTIMACIONES (se estarian ejecunatdo del mes 3 hasta el final con el
ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO
CONCEPTOCONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 H
DESCRIPCION
ACERO DE REFUERZO DEL No. 3 (3/8")ACERO DE REFUERZO DEL No. 6 (3/4")ALAMBRE RECOCIDOPOLIN DE MADERA DE PINO DE 3RA DE 4" x 4" x 8'BARROTE DE MADERA DE PNO DE 3RA DE 2" x 4" x 8'DUELA DE MADERA DE PINO DE 3RA DE 1" x 4" x 8'CLAVOS DE 2 1/2" HASTA 4"DIESELMEMBRANA DE CURADO
CUADRILLA DE 1 OFICIAL ALBAÑIL + 5 AYUDANTES DE ALBAÑIL + CABO DE OFICIOSCUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS
MAQUINARIA Y EQUIPOVIBRADOR PARA CONCRETO DE 5.5 HP
HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDADHERRAMIENTA DE MANOEQUIPO DE SEGURIDAD
SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD
FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO
Ó UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %)
(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES
MATERIALES (ART. 193 RLOPSRM) (Materiales de adquisicion)
MANO DE OBRA (ART. 190 RLOPSRM)
CUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEGRA + CABO DE OFICIOS
BASICOS DE MATERIALES (ART. 193 RLOPSRM) (Materiales fabricados en sitio)CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8HP), AGREGADO MAXIMO DE 3/4"
TASA DE INTERES ANUALTASA DE INTERES MENSUAL
TASA DE INTERES A 4.5 MESESCONSIDERANDO UN ANTICIPO (con el anticipo se ejecuta un 1er mes)
CONSIDERANDO PAGO DE ESTIMACIONES (se estarian ejecunatdo del mes 3 hasta el final con el cobro de estimaciones)
CUANTIFICACIONUNIDAD CONCRETO
CONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 H PZA ZAPATA = 2.00 MTS x 2.00 MTS x 0.20 MTSDADO = 0.50 MTS x 0.50 MTS x 1.60 MTS
UNIDAD COSTO CANTIDAD IMPORTE TOTAL = 0.80 M3 + 0.40 M3 + 2% DESPERDICIO
TON $10,500.00 * 0.081 $850.50 CALCULO RENDIMIENTO PARA CUADRILLA DE 1 OF. ALBAÑIL + 5 AYUD. ALBAÑILTON $10,500.00 * 0.053 $556.50 1.22 M3 DE CONCRETOKG $11.50 * 6.03 $69.35 1,220.00 LTS DE CONCRETOPZA $96.60 * 1.60 $154.56 65.00 BOTES / 5 AYUDANTESPZA $52.90 * 1.60 $84.64 13 VUELTAS x 50 SEGUNDOSPZA $32.20 * 6.67 $214.67 650.00 SEGUNDOS / 60 SEGKG $16.00 * 2.00 $32.00 TIEMPO PARA VIBRADOLT $11.54 * 2.40 $27.70 NIVELADO Y EMPAREJADOLT $27.00 * 2.40 $64.80 VACIADO DE CONCRETO
COLADO DE ZAPATASUBTOTAL DE MATERIALES $2,054.71 RENDIMIENTO = 8.00 HRS / 0.50 HRS
RENDIMIENTO EN CONDICIONES NORMALES DE EJECUCION (BASE DE DATOS NEODATA)JORNADA $2,105.61 / 4.10 $513.77 5.00 M3 / JOR JORNADA $997.24 / 1.50 $663.16 0.20 TON / JORJORNADA $997.24 / 1.88 $531.86 9.00 M2 / JOR
SUBTOTAL DE MANO DE OBRA $1,708.79 ACERODESTAJO MAXIMO $987.74 ZAPATA (VARILLA DEL No. 3)
HORA $54.58 / 0.5125 $106.50 L=2.00 MTS / 0.15 MTS14.00ø x 2.00 MTS x 2 SENTIDOS x 2 LECHOS
SUBTOTAL DE MAQUINARIA Y EQUIPO $106.50 112.00 ML x 0.557 KG/ML + 5% DESPERDICIO65.50 KG/1000 KG
% $1,708.79 * 0.03 $51.26% $1,708.79 * 0.02 $34.18 DADO (VARILLA DEL No. 6)
SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD $85.44 LONG. VARILLA = 1.60 MTS (dado)+0.20MTS(zapata)+1.00MT (escuadra)LONG. VARILLA =
M3 $1,246.21 * 1.22 $1,520.37 2.80 ML x 8.00ø x 2.25 KG/ML
50.40 KG + 5% DESPERDICIOSUBTOTAL DE BASICOS DE MATERIALES $1,520.37 52.92 KG / 1000 KG
COSTO DIRECTO $5,475.82 DADO (VARILLA DEL No. 3)% DE INDIRECTOS 17.4934% $957.91 LONG. ESTRIBOS = 0.46 MTS x 4 LADOS
SUBTOTAL 1 $6,433.73 ALTURA DADO= 1.60 MTS / 0.12 MTS SEPARACION
% DE FINANCIAMIENTO 0.3543% $22.79 14.00ø x 1.84 ML x 0.557 KG/ML + 5% DESPERDICIOSUBTOTAL 2 $6,456.52 15.07 KG/1000 KG
% DE UTILIDAD 10.0000% $645.65SUBTOTAL 3 $7,102.17 TOTALES
(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES 0.5000% $35.51 ø#3 = 0.066 TON + 0.015 TON
PRECIO UNITARIO $7,137.68 ø#6 = 0.053 TON
CIMBRAZAPATA = 2.00 MTS x 0.20 MTS x 4 LADOSDADO = 0.50 MTS x 1.60 MTS x 4 LADOS
1 PT = LARGO EN PULGADAS x ANCHO EN PULGADAS x ALTURA EN PIE / 12
CETES PT DE POLIN = 4" x 4" x 8' / 122.80%0.23%1.05% financiando los 4.5 meses0.82% se estarian financiando 3.5 mes KG DE ALAMBRE x TON DE ACERO ARMADO0.23% se estraria financiando 1 solo mes PARA VARILLA DEL No. 2.5 Y 3
PARA VARILLA DEL No. 4 Y 6PARA VARILLA DEL No. 6 EN ADELANTE
CUANTIFICACION
ZAPATA = 2.00 MTS x 2.00 MTS x 0.20 MTS 0.80 M3DADO = 0.50 MTS x 0.50 MTS x 1.60 MTS 0.40 M3TOTAL = 0.80 M3 + 0.40 M3 + 2% DESPERDICIO 1.22 M3
CALCULO RENDIMIENTO PARA CUADRILLA DE 1 OF. ALBAÑIL + 5 AYUD. ALBAÑIL1.22 M3 DE CONCRETO = 1220.00 LTS1,220.00 LTS DE CONCRETO = 64.21 BOTES65.00 BOTES / 5 AYUDANTES 13.00 VUELTAS13 VUELTAS x 50 SEGUNDOS 650.00 SEGUNDOS650.00 SEGUNDOS / 60 SEG 10.83 MINUTOSTIEMPO PARA VIBRADO 10.00 MINUTOSNIVELADO Y EMPAREJADO 10.00 MINUTOSVACIADO DE CONCRETO 15.00 MINUTOSCOLADO DE ZAPATA 45.83 MINUTOSRENDIMIENTO = 8.00 HRS / 0.50 HRS 10.67 ZAPATAS
RENDIMIENTO EN CONDICIONES NORMALES DE EJECUCION (BASE DE DATOS NEODATA)
ZAPATA (VARILLA DEL No. 3)L=2.00 MTS / 0.15 MTS 13 14.00 ø14.00ø x 2.00 MTS x 2 SENTIDOS x 2 LECHOS 112.00 ML112.00 ML x 0.557 KG/ML + 5% DESPERDICIO 65.50 KG65.50 KG/1000 KG 0.066 TON
DADO (VARILLA DEL No. 6)LONG. VARILLA = 1.60 MTS (dado)+0.20MTS(zapata)+1.00MT (escuadra)LONG. VARILLA = 2.80 ML2.80 ML x 8.00ø x 2.25 KG/ML 50.40 KG
50.40 KG + 5% DESPERDICIO 52.92 KG52.92 KG / 1000 KG 0.053 TON
DADO (VARILLA DEL No. 3)LONG. ESTRIBOS = 0.46 MTS x 4 LADOS 1.84 MLALTURA DADO= 1.60 MTS / 0.12 MTS SEPARACION 13.33 14.00 ø14.00ø x 1.84 ML x 0.557 KG/ML + 5% DESPERDICIO 15.07 KG15.07 KG/1000 KG 0.015 TON
ø#3 = 0.066 TON + 0.015 TON 0.081 TON
ø#6 = 0.053 TON 0.053 TONTOTAL 0.133 TON
ZAPATA = 2.00 MTS x 0.20 MTS x 4 LADOS 1.60 M2DADO = 0.50 MTS x 1.60 MTS x 4 LADOS 3.20 M2
TOTAL 4.80 M2
1 PT = LARGO EN PULGADAS x ANCHO EN PULGADAS x ALTURA EN PIE / 12
PT DE POLIN = 4" x 4" x 8' / 12 10.66666667 PT$8.00
$85.33
KG DE ALAMBRE x TON DE ACERO ARMADOPARA VARILLA DEL No. 2.5 Y 3 50 KG ALAMBRE / TONPARA VARILLA DEL No. 4 Y 6 40 KG ALAMBRE / TONPARA VARILLA DEL No. 6 EN ADELANTE 30 KG ALAMBRE / TON
75 PZAS / KG CLAVOS DE 4"249 PZAS / KG CLAVOS DE 2 1/2"
ANALISIS, CALCULO E INTEGRACION DE CUADRILLAS
CLAVE CONCEPTOMO1A1AA CUADRILLA DE 1 OFICIAL ALBAÑIL + 5 AYUDANTES DE ALBAÑIL + CABO DE OFICIOS
CLAVE DESCRIPCION UNIDADSn=SALARIO TABULADO
MOALB OFICIAL ALBAÑIL JORNADAMOAYUA AYUDANTE DE ALBAÑIL JORNADAMOCAB CABO DE OFICIOS JORNADA
SUBTOTAL DE MANO DE OBRA
CLAVE CONCEPTOMO1F1AF CUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS
CLAVE DESCRIPCION UNIDADSn=SALARIO TABULADO
MOFIE OFICIAL FIERRERO JORNADAMOAYUF AYUDANTE DE FIERRERO JORNADAMOCAB CABO DE OFICIOS JORNADA
SUBTOTAL DE MANO DE OBRA
CLAVE CONCEPTOMO1C1AC CUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEGRA
CLAVE DESCRIPCION UNIDADSn=SALARIO TABULADO
MOCAR CARPINTERO DE OBRA NEGRA JORNADAMOAYUC AYUDANTE DE CARPINTERO DE OBRA NEGRA JORNADAMOCAB CABO DE OFICIOS JORNADA
SUBTOTAL DE MANO DE OBRA
OFICIAL ALBAÑIL
SALARIO DE ACUERDO A LA COMISION NACIONAL DE SALARIOS MINIMOS (Sala
SALARIO DE ACUERDO A TABULADORES DE SINDICATOS (Contrato Colectivo)
Sn = SALARIO TABULADO
MANO DE OBRA (ART. 190 RLOPSRM)
MANO DE OBRA (ART. 190 RLOPSRM)
MANO DE OBRA (ART. 190 RLOPSRM)
ANALISIS, CALCULO E INTEGRACION DE CUADRILLAS
UNIDAD CLAVECUADRILLA DE 1 OFICIAL ALBAÑIL + 5 AYUDANTES DE ALBAÑIL + CABO DE OFICIOS JORNADA MO1A1AA
COSTO CANTIDAD IMPORTE CLAVESn=SALARIO TABULADO
$314.29 * 1.00 $314.29 MOALB$171.43 * 1.00 $171.43 MOAYUA$357.14 * 0.10 $35.71 MOCAB
SUBTOTAL DE MANO DE OBRA $521.43
UNIDAD CLAVECUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS JORNADA MO1F1AF
COSTO CANTIDAD IMPORTE CLAVESn=SALARIO TABULADO
$342.86 * 1.00 $342.86 MOFIE$200.00 * 1.00 $200.00 MOAYUF$357.14 * 0.10 $35.71 MOCAB
SUBTOTAL DE MANO DE OBRA $578.57
UNIDAD CLAVECUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEGRA JORNADA MO1C1AC
COSTO CANTIDAD IMPORTE CLAVESn=SALARIO TABULADO
$342.86 * 1.00 $342.86 MOCAR$200.00 * 1.00 $200.00 MOAYUC$357.14 * 0.10 $35.71 MOCAB
SUBTOTAL DE MANO DE OBRA $578.57
JOR SEMANA CLAVEMO1A2AA
$98.05 $686.35CLAVE
$180.00 $1,260.00MOALB
$314.29 $2,200.03 MOAYUAMOCAB
ANALISIS, CALCULO E INTEGRACION DE CUADRILLAS
CONCEPTOCUADRILLA DE 1 OFICIAL ALBAÑIL + 5 AYUDANTES DE ALBAÑIL + CABO DE OFICIOS
DESCRIPCION UNIDAD COSTOSr=SALARIO REAL
OFICIAL ALBAÑIL JORNADA $539.85 *AYUDANTE DE ALBAÑIL JORNADA $300.92 *CABO DE OFICIOS JORNADA $611.64 *
SUBTOTAL DE MANO DE OBRA
CONCEPTOCUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS
DESCRIPCION UNIDAD COSTOSr=SALARIO REAL
OFICIAL FIERRERO JORNADA $587.71 *AYUDANTE DE FIERRERO JORNADA $348.36 *CABO DE OFICIOS JORNADA $611.64 *
SUBTOTAL DE MANO DE OBRA
CONCEPTOCUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEG
DESCRIPCION UNIDAD COSTOSr=SALARIO REAL
CARPINTERO DE OBRA NEGRA JORNADA $587.71 *AYUDANTE DE CARPINTERO DE OBRA NEGRA JORNADA $348.36 *CABO DE OFICIOS JORNADA $611.64 *
SUBTOTAL DE MANO DE OBRA
CONCEPTOCUADRILLA DE 1 OFICIAL ALBAÑIL + 2 AYUDANTES DE ALBAÑIL + CABO DE OFICIOS
DESCRIPCION UNIDAD COSTOSr=SALARIO REAL
OFICIAL ALBAÑIL JORNADA $539.85 *AYUDANTE DE ALBAÑIL JORNADA $300.92 *CABO DE OFICIOS JORNADA $611.64 *
SUBTOTAL DE MANO DE OBRA
MANO DE OBRA (ART. 190 RLOPSRM)
MANO DE OBRA (ART. 190 RLOPSRM)
MANO DE OBRA (ART. 190 RLOPSRM)
MANO DE OBRA (ART. 190 RLOPSRM)
UNIDADJORNADA
CANTIDAD IMPORTE
1.00 $539.855.00 $1,504.600.10 $61.16
SUBTOTAL DE MANO DE OBRA $2,105.61
UNIDADJORNADA
CANTIDAD IMPORTE
1.00 $587.711.00 $348.360.10 $61.16
SUBTOTAL DE MANO DE OBRA $997.24
UNIDADCUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEG JORNADA
CANTIDAD IMPORTE
1.00 $587.711.00 $348.360.10 $61.16
SUBTOTAL DE MANO DE OBRA $997.24
UNIDADJORNADA
CANTIDAD IMPORTE
1.00 $539.852.00 $601.840.10 $61.16
SUBTOTAL DE MANO DE OBRA $1,202.85
se deberá entender al factor de salario real “Fsr”como la relación de los días realmente pagados en un periodo anual, de enero a diciembre, divididosentre los días efectivamente laborados durante el mismo periodo, de acuerdo con la siguiente expresión:
FSR = [ Ps ( Tp / Tl ) ] + ( Tp / Tl )
Donde:“Fsr” Representa el factor de salario real.“Ps” Representa, en fracción decimal, las obligaciones obrero-patronales derivadas de la Ley delSeguro Social y de la Ley del Instituto del Fondo Nacional de la Vivienda para losTrabajadores.“Tp” Representa los días realmente pagados durante un periodo anual.“Tl” Representa los días realmente laborados durante el mismo periodo anual utilizado en Tp.
CALCULO DE LA VARIABLE "Tl" (DIAS REALMENTE LABORADOS DURANTE EL PERIODO ANUAL)
DIAS CALENDARIOMENOS DIAS NO LABORADOS AL AÑO
DIAS POR COSTUMBREDIAS POR CLIMA (LLUVIAS)DIAS POR SINDICATO (de acuerdo al Contrato Colectivo)DIAS POR PERMISO Y ENFERMEDAD NO PROFESIONALDIAS EQUIVALENTES POR ARRASTREDIAS POR GUARDIA (contratos pemex (plataformas))
TOTAL DIAS NO LABORADOS AL AÑO
"Tl" = DIAS CALENDARIO - TOTAL DIAS NO LABORADOS AL AÑO
CALCULO DE LA VARIABLE "Tp" ( DIAS REALMENTE PAGADOS EN UN PERIODO ANUAL)
DIAS CALENDARIO
HORAS EXTRAS (PARA TRABAJOS DE EMERGENCIA)TOTAL DE DIAS PAGADOS EN UN PERIODO ANUAL
CALCULO DE LA VARIABLE "Ps" (OBLIGACIONES OBRERO-PATRONALES DERIVADAS DE LA LEY DEL IMSS E INFONAVIT)
PARA APLICAR ESTAS OBLIGACIONES O PRESTACIONES DEL IMSS E INFONAVIT SE DEBE CALCULAR UN SALARIO BASE DE COTIZACION
ANALISIS, CALCULO E INTEGRACION DEL FACTOR DE SALARIO REAL (ART. 191 RLOPSRM)
DIAS DE DESCANSO OBLIGATORIO (Domingos) (ART. 69 LFT)DIAS FESTIVOS POR LEY (ART. 74 LFT)DIAS LUNES POR LEY (ART. 74 LFT)VACACIONES (ART. 76 LFT)
AGUINALDO (ART. 87 LFT)PRIMA VACACIONAL (ART. 80 LFT) (25% DE 6 DIAS DE VACACIONES)
SALARIO BASE DE COTIZACION (SBC) = SALARIO TABULADO (Sn) x FACTOR SALARIO BASE DE COTIZACION (FSBC)FSBC = DIAS REALMENTE PAGADOS EN UN PERIODO ANUAL / DIAS CALENDARIOFSBC = 381.50 DIAS / 365.00 DIAS
SALARIO MINIMO GENERAL VIGENTE DEL DF (SMGVDF) $67.293 VECES EL SALARIO MINIMO GENERAL VIGENTE DEL DF (3VSMGVDF) $201.87
CATEGORIA
A B C DSn FSBC SBC
Sn x FSBCB x C
OFICIAL ALBAÑIL $314.29 1.0452 $328.50AYUDANTE DE ALBAÑIL $171.43 1.0452 $179.18CABO DE OFICIOS $357.14 1.0452 $373.28OFICIAL FIERRERO $342.86 1.0452 $358.36AYUADNTE DE FIERRERO $200.00 1.0452 $209.04OFICIAL CARPINTERO DE O. N. $342.86 1.0452 $358.36AYUDANTE DE CARPINTERO DE O. N. $200.00 1.0452 $209.04OPERADOR DE REVOLVEDORA $190.00 1.0452 $198.59
El salario base de cotización se integra con los pagos hechos en efectivo por cuotadiaria, gratificaciones, percepciones, alimentación, habitación, primas, comisiones, prestaciones enespecie y cualquiera otra cantidad o prestación que se entregue al trabajador por su trabajo
El régimen obligatorio comprende los seguros de:I. Riesgos de trabajo;II. Enfermedades y maternidad;III. Invalidez y vida;IV. Retiro, cesantía en edad avanzada y vejez, yV. Guarderías y prestaciones sociales.
ART. 106 FRACC. I LEY DEL IMSSCUOTA FIJA 13.90%
CADA AÑO AUMENTA 0.65%
1998 13.90%1999 14.55%2000 15.20%
SALARIO TABULADO
FACTOR DE SALARIO BASE DE
COTIZACION
SALARIO BASE DE
COTIZACION
SALARIO BASE DE COTIZACION : (Artículo 27 LEY DEL IMSS)
PRESTACIONES OBLIGATORIAS PARA INCLUIR EN EL CALCULO Artículo 11 LEY DEL IMSS
2001 15.85%2002 16.50%2003 17.15%2004 17.80%2005 18.45%2006 19.10%2007 19.75%2008 20.40%
2009 20.40%2010 20.40%2011 20.40%2012 20.40%2013 20.40%2014 20.40%
ART. DECIMONOVENO
TRANSITORIOLEY DEL
IMSS
ART. SEGUNDOTRANSITORIO
LEY DELIMSS
como la relación de los días realmente pagados en un periodo anual, de enero a diciembre, divididosentre los días efectivamente laborados durante el mismo periodo, de acuerdo con la siguiente expresión:
FSR = [ Ps ( Tp / Tl ) ] + ( Tp / Tl )
“Ps” Representa, en fracción decimal, las obligaciones obrero-patronales derivadas de la Ley del
“Tl” Representa los días realmente laborados durante el mismo periodo anual utilizado en Tp.
CALCULO DE LA VARIABLE "Tl" (DIAS REALMENTE LABORADOS DURANTE EL PERIODO ANUAL)AÑO 2014
365.00
52.004.00 1 ENERO, 1 MAYO, 16 SEPTIEMBRE, 25 DICIEMBRE
3.00 1er lunes FEBRERO, 3er lunes MARZO, 3er lunes NOVIEMBRE
6.002.00 VIERNES SANTO, 12 DICIEMBRE, 3 DE MAYO, 2 NOVIEMBRE
4.000.000.000.000.00
TOTAL DIAS NO LABORADOS AL AÑO 71.00
294.00 "Tl"
CALCULO DE LA VARIABLE "Tp" ( DIAS REALMENTE PAGADOS EN UN PERIODO ANUAL)
365.0015.001.500.00
TOTAL DE DIAS PAGADOS EN UN PERIODO ANUAL 381.50 "Tp"
CALCULO DE LA VARIABLE "Ps" (OBLIGACIONES OBRERO-PATRONALES DERIVADAS DE LA LEY DEL IMSS E INFONAVIT)
PARA APLICAR ESTAS OBLIGACIONES O PRESTACIONES DEL IMSS E INFONAVIT SE DEBE CALCULAR UN SALARIO BASE DE COTIZACION
(ART. 191 RLOPSRM)
SALARIO BASE DE COTIZACION (SBC) = SALARIO TABULADO (Sn) x FACTOR SALARIO BASE DE COTIZACION (FSBC)
1.0452 FSBC
CUOTA FIJA
E F G H I J1.50% 20.40% 0.95% 1.425% 2.375%
SBC-3VSMGDFF x E G x SMGVDG H x D I x D J x D
$126.63 $1.90 $13.73 $3.12 $4.68 $7.80$13.73 $1.70 $2.55 $4.26
$171.41 $2.57 $13.73 $3.55 $5.32 $8.87$156.49 $2.35 $13.73 $3.40 $5.11 $8.51
$7.17 $0.11 $13.73 $1.99 $2.98 $4.96$156.49 $2.35 $13.73 $3.40 $5.11 $8.51
$7.17 $0.11 $13.73 $1.99 $2.98 $4.96$13.73 $1.89 $2.83 $4.72
El salario base de cotización se integra con los pagos hechos en efectivo por cuotadiaria, gratificaciones, percepciones, alimentación, habitación, primas, comisiones, prestaciones enespecie y cualquiera otra cantidad o prestación que se entregue al trabajador por su trabajo
ART. 106 FRACC. II LEY DEL IMSSEXCEDENTE DE 3 VECES SALARIO MINIMO 8.00%
CADA AÑO REDUCE 0.65%
1998 8.00%1999 7.35%2000 6.70%
ART. 106 FRACC. II LEY DEL IMSS
ART. 106 FRACC. I LEY
DEL IMSS
ART. 107 FRACC. I Y II LEY DEL IMSS
ART. 25 PARRAFO II LEY
DEL IMSS
ART. 147 LEY DEL IMSS
EXCEDENTE DE 3 VECES EL SALARIO
MINIMO GENERAL DEL D.F.
% AL EXCEDENTE DE 3 VECES EL SALARIO
MINIMO GENERAL DEL D.F.
PRESTACIONES EN DINERO
PRESTACIONES EN ESPECIE DE
LOS PENSIONADOS
INVALIDEZ Y VIDA
Artículo 11 LEY DEL IMSS
2001 6.05%2002 5.40%2003 4.75%2004 4.10%2005 3.45%2006 2.80%2007 2.15%2008 1.50%
2009 1.50%2010 1.50%2011 1.50%2012 1.50%2013 1.50%2014 1.50%
ART. DECIMONOVENO
TRANSITORIOLEY DEL
IMSS
ART. SEGUNDOTRANSITORIO
LEY DELIMSS
1er lunes FEBRERO, 3er lunes MARZO, 3er lunes NOVIEMBRE
GUARDERIAS
K L M N O P4.275% 1.00% 7.58875% 2.00% 5.00% 3.00%
K x D L x D M x D N x D O x D P x D
$14.04 $3.28 $24.93 $6.57 $16.42 $9.85$7.66 $1.79 $13.60 $3.58 $8.96 $5.38
$15.96 $3.73 $28.33 $7.47 $18.66 $11.20$15.32 $3.58 $27.19 $7.17 $17.92 $10.75$8.94 $2.09 $15.86 $4.18 $10.45 $6.27
$15.32 $3.58 $27.19 $7.17 $17.92 $10.75$8.94 $2.09 $15.86 $4.18 $10.45 $6.27$8.49 $1.99 $15.07 $3.97 $9.93 $5.96
ART. 168 FRACC. II LEY
DEL IMSS
ART. 211 Y 212 LEY DEL IMSS
ART. 73 Y 74 LEY DEL IMSS
ART. 168 FRACC. I LEY
DEL IMSS
ART. 29 FRACC. II LEY DEL
INFONATVIT
ART. 158 CODIGO FISCAL DEL DF
CESANTIA EN EDAD
AVANZADA Y VEJEZ
RIESGO DE TRABAJO
SISTEMA DE AHORRO PARA
EL RETIRO (SAR)
INSTITUTO DEL FONDO NACIONAL
PARA LA VIVIENDA DE LOS TRABAJADORES
IMPUESTO SOBRE NOMINA
Ps EN FACTOR Ps ( Tp / Tl )
Q R S T U VPs Ps / SBC FSI FSR Sn x FSR
SUMA F:P Q / D R x S T + S
$106.34 0.3237 1.2976 0.4200 1.7177 $539.85$63.21 0.3527 1.2976 0.4577 1.7554 $300.92$119.38 0.3198 1.2976 0.4150 1.7126 $611.64$115.03 0.3210 1.2976 0.4165 1.7141 $587.71$71.56 0.3423 1.2976 0.4442 1.7418 $348.36$115.03 0.3210 1.2976 0.4165 1.7141 $587.71$71.56 0.3423 1.2976 0.4442 1.7418 $348.36$68.57 0.3453 1.2976 0.4480 1.7456 $331.67
$730.66 1.98$3,653.32
135.00$493,197.65
SUMA DE PRESTACIONES
Tp / Tl = FACTOR DE SALARIO
INTEGRADO
FSR = [ Ps ( Tp / Tl ) ] + ( Tp / Tl )
SALARIO REAL
ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO
CLAVEMACON250
CLAVE
MACEMMAGRAMAAREMAAGU
MO1A2AA
EQREV
HEREQS
ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO
CONCEPTOCONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8HP), AGREGADO MAXIMO DE 3/4"
DESCRIPCION
CEMENTO GRIS PORTLAND TIPO II PUZOLANICOGRAVA DE MINA T.M.A. 19 MM Ø (3/4), M3ARENA DE MINAAGUA DE PIPA
CUADRILLA DE 1 OFICIAL ALBAÑIL + 2 AYUDANTES DE ALBAÑIL + CABO DE OFICIOS
MAQUINARIA Y EQUIPOREVOLVEDORA PARA CONCRETO DE 1 SACO (8 HP)
HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDADHERRAMIENTA DE MANOEQUIPO DE SEGURIDAD
SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD
MANO DE OBRA (ART. 190 RLOPSRM)
BASICOS DE MATERIALES (ART. 193 RLOPSRM) (Materiales fabricados en sitio)
UNIDADCONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8HP), AGREGADO MAXIMO DE 3/4" M3
UNIDAD COSTO CANTIDAD IMPORTE
TON $1,900.00 * 0.39 $741.00M3 $242.90 * 0.63 $153.03M3 $228.60 * 0.53 $121.16M3 $60.00 * 0.21 $12.60
SUBTOTAL DE MATERIALES $1,027.79
JORNADA $1,202.85 / 8.00 $150.36
SUBTOTAL DE MANO DE OBRA $150.36DESTAJO MAXIMO $86.91
HORA $60.55 / 1.00 $60.55
SUBTOTAL DE MAQUINARIA Y EQUIPO $60.55
% $150.36 * 0.03 $4.51% $150.36 * 0.02 $3.01
SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD $7.52
SUBTOTAL DE BASICOS DE MATERIALES
COSTO DIRECTO $1,246.21
ANALISIS, CALCULO E INTEGRACION DEL COSTO HORARIO
COSTO HORARIO COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS
DEPRECIACIONCOSTOS INVERSIONFIJOS SEGUROS
MANTENIMIENTO
COSTO COMBUSTIBLESHORARIO COSTOS POR LUBRICANTES OTROS CONSUMOS
CONSUMO LLANTAS OTRAS FUENTES DE ENERGIA (Energia electrica)PIEZAS ESPECIALES
COSTOS POR SALARIOS DEOPERACIÓN OPERACIÓN
CLAVE DESCRIPCIONEQREV REVOLVEDORA PARA CONCRETO DE 1 SACO
DATOS GENERALESVALOR DE ADQUISICION $10,500.00 POTENCIA DEL MOTOR EN HPPn=VALOR DE LAS LLANTAS (JGO) $1,000.00 % DE OPERACIÓNVm=VALOR DE LA MAQUINA $9,500.00 COEFICIENTE DE CONSUMO (Gasolina)Hea=HORAS TRABAJADAS POR AÑO 2,000.00 Pc=PRECIO DE COMBUSTIBLE (Gasolina)Ve=VIDA ECONOMICA EN HORAS 10,000.00 COEFICIENTE DE CONSUMO (Aceite)% DE RESCATE 20.00% CAPACIDAD DEL CARTER EN LTSVr=VALOR DE RESCATE $2,100.00 HORAS ENTRE CAMBIOS SUCESIVOSi=TASA DE INTERES ANUAL 2.80% Pa=PRECIO DEL ACEITE (Motor gasolina)INDICADOR ECONOMICO ESPECIFICO CETES Vn=VIDA ECONOMICA DE LLANTAS EN HRS
s=PRIMA ANUAL PROMEDIO DE SEGUROS 6.00% Sr= SALARIO REAL DEL OPERADOR DE REVOLVEDORA
Ko=COEFICIENTE DE MANTENIMIENTO 0.55 Ht=HORAS EFECTIVAS DE TRABAJO
D = ( Vm - Vr ) / VeD = ( $9,500.00 - $2,100.00 ) / 10,000.00 HRS
Im = [ ( Vm + Vr ) i ] / ( 2 x Hea )Im = [ ( $9,500.00 + $2,100.00 ) 2.80% ] / ( 2 x 2,000.00 )
Sm = [ ( Vm + Vr ) s ] / ( 2 x Hea )
COSTOS FIJOS (ART. 195 RLOPSRM)DEPRECIACION (ART. 196 RLOPSRM)
INVERSION (ART. 197 RLOPSRM)
SEGUROS (ART. 198 RLOPSRM)
Sm = [ ( $9,500.00 + $2,100.00 ) 6.00% ] / ( 2 x 2,000.00 )
Mn = Ko x DMn = 0.55 x $ 0.74
TOTAL COSTOS FIJOS
Co = Gh x PcGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Gasolina)Gh = 8.00 HP x 80.00% x 0.2271 1.45 LTS/HRCo = 1.45 LTS/HR x $11.09
Lb = ( Ah + Ga ) PaAh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Aceite)Ga = CAPACIDAD DEL CARTER EN LTS / HORAS ENTRE CAMBIOS SUCESIVOSAh = 8.00 HP x 80.00% x 0.003 0.019 LTS/HRGa = 2.00 LTS / 350.00 HRS 0.006 LTS/HRLb = ( 0.019 LTS/HR + 0.006 LTS/HR ) $55.00
N = Pn / VnN = $1,000.00 / 5,000.00 HRS
TOTAL COSTOS POR CONSUMO
Po = Sr / HtPo = $331.67 / 8.00 HRS
TOTAL COSTOS POR OPERACIÓN
TOTAL COSTO HORARIO
MANTENIMIENTO (ART. 199 RLOPSRM)
COSTOS POR CONSUMOS (ART. 200 RLOPSRM)COMBUSTIBLES (ART. 201 RLOPSRM)
LUBRICANTES (ART. 203 RLOPSRM)
LLANTAS (ART. 204 RLOPSRM)
COTSOS POR OPERACIÓN (ART. 206 RLOPSRM)OPERACIÓN (ART. 206 RLOPSRM)
COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS
OTRAS FUENTES DE ENERGIA (Energia electrica)
UNIDADHORA
POTENCIA DEL MOTOR EN HP 8.0080.00%
COEFICIENTE DE CONSUMO (Gasolina) 0.2271Pc=PRECIO DE COMBUSTIBLE (Gasolina) $11.09COEFICIENTE DE CONSUMO (Aceite) 0.003CAPACIDAD DEL CARTER EN LTS 2.00HORAS ENTRE CAMBIOS SUCESIVOS 350.00Pa=PRECIO DEL ACEITE (Motor gasolina) $55.00Vn=VIDA ECONOMICA DE LLANTAS EN HRS 5,000.00Sr= SALARIO REAL DEL OPERADOR DE REVOLVEDORA $331.67 Sn= $ 190.00Ht=HORAS EFECTIVAS DE TRABAJO 8.00
$0.74 10,000.00 $7,400.00$2,100.00$9,500.00
$0.08 10,000.00 $812.00
$0.17 10,000.00 $1,740.00
$0.41 10,000.00 $4,070.00
TOTAL COSTOS FIJOS $1.40
$400.00 POR SERVICIOS$800.00 POR 2 SERVICIOS AL AÑO
$4,000.00 POR SERVICIOS EN 5 AÑOSGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Gasolina)
$16.12
Ah = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Aceite)
$1.37
$0.20
TOTAL COSTOS POR CONSUMO $17.69
$41.46TOTAL COSTOS POR OPERACIÓN $41.46
TOTAL COSTO HORARIO $60.55
POR SERVICIOS EN 5 AÑOS
ANALISIS, CALCULO E INTEGRACION DEL COSTO HORARIO
COSTO HORARIO COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS
DEPRECIACIONCOSTOS INVERSIONFIJOS SEGUROS
MANTENIMIENTO
COSTO COMBUSTIBLESHORARIO COSTOS POR LUBRICANTES OTROS CONSUMOS
CONSUMO LLANTAS OTRAS FUENTES DE ENERGIA (Energia electrica)PIEZAS ESPECIALES
COSTOS POR SALARIOS DEOPERACIÓN OPERACIÓN
CLAVE DESCRIPCIONEQVIB VIBRADOR PARA CONCRETO
DATOS GENERALESVALOR DE ADQUISICION $6,550.00 POTENCIA DEL MOTOR EN HPPn=VALOR DE LAS LLANTAS (JGO) $0.00 % DE OPERACIÓNVm=VALOR DE LA MAQUINA $6,550.00 COEFICIENTE DE CONSUMO (Gasolina)Hea=HORAS TRABAJADAS POR AÑO 2,000.00 Pc=PRECIO DE COMBUSTIBLE (Gasolina)Ve=VIDA ECONOMICA EN HORAS 8,000.00 COEFICIENTE DE CONSUMO (Aceite)% DE RESCATE 10.00% CAPACIDAD DEL CARTER EN LTSVr=VALOR DE RESCATE $655.00 HORAS ENTRE CAMBIOS SUCESIVOSi=TASA DE INTERES ANUAL 2.80% Pa=PRECIO DEL ACEITE (Motor gasolina)INDICADOR ECONOMICO ESPECIFICO CETES Vn=VIDA ECONOMICA DE LLANTAS EN HRS
s=PRIMA ANUAL PROMEDIO DE SEGUROS 6.00% Sr= SALARIO REAL DEL OPERADOR DE VIBRADOR
Ko=COEFICIENTE DE MANTENIMIENTO 0.40 Ht=HORAS EFECTIVAS DE TRABAJO
D = ( Vm - Vr ) / VeD = ( $9,500.00 - $2,100.00 ) / 10,000.00 HRS
Im = [ ( Vm + Vr ) i ] / ( 2 x Hea )Im = [ ( $9,500.00 + $2,100.00 ) 2.80% ] / ( 2 x 2,000.00 )
Sm = [ ( Vm + Vr ) s ] / ( 2 x Hea )
COSTOS FIJOS (ART. 195 RLOPSRM)DEPRECIACION (ART. 196 RLOPSRM)
INVERSION (ART. 197 RLOPSRM)
SEGUROS (ART. 198 RLOPSRM)
Sm = [ ( $9,500.00 + $2,100.00 ) 6.00% ] / ( 2 x 2,000.00 )
Mn = Ko x DMn = 0.55 x $ 0.74
TOTAL COSTOS FIJOS
Co = Gh x PcGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Gasolina)Gh = 8.00 HP x 80.00% x 0.2271 1.00 LTS/HRCo = 1.45 LTS/HR x $11.09
Lb = ( Ah + Ga ) PaAh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Aceite)Ga = CAPACIDAD DEL CARTER EN LTS / HORAS ENTRE CAMBIOS SUCESIVOSAh = 8.00 HP x 80.00% x 0.003 0.013 LTS/HRGa = 2.00 LTS / 350.00 HRS 0.002 LTS/HRLb = ( 0.019 LTS/HR + 0.006 LTS/HR ) $55.00
N = Pn / VnN = $1,000.00 / 5,000.00 HRS
TOTAL COSTOS POR CONSUMO
Po = Sr / HtPo = $331.67 / 8.00 HRS
TOTAL COSTOS POR OPERACIÓN
TOTAL COSTO HORARIO
MANTENIMIENTO (ART. 199 RLOPSRM)
COSTOS POR CONSUMOS (ART. 200 RLOPSRM)COMBUSTIBLES (ART. 201 RLOPSRM)
LUBRICANTES (ART. 203 RLOPSRM)
LLANTAS (ART. 204 RLOPSRM)
COTSOS POR OPERACIÓN (ART. 206 RLOPSRM)OPERACIÓN (ART. 206 RLOPSRM)
COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS
OTRAS FUENTES DE ENERGIA (Energia electrica)
UNIDADHORA
POTENCIA DEL MOTOR EN HP 5.5080.00%
COEFICIENTE DE CONSUMO (Gasolina) 0.2271Pc=PRECIO DE COMBUSTIBLE (Gasolina) $11.09COEFICIENTE DE CONSUMO (Aceite) 0.003CAPACIDAD DEL CARTER EN LTS 0.80HORAS ENTRE CAMBIOS SUCESIVOS 350.00Pa=PRECIO DEL ACEITE (Motor gasolina) $55.00Vn=VIDA ECONOMICA DE LLANTAS EN HRS 0.00Sr= SALARIO REAL DEL OPERADOR DE VIBRADOR $331.67 Sn= $ 190.00Ht=HORAS EFECTIVAS DE TRABAJO 8.00
$0.74 10,000.00 $7,368.75$2,100.00$9,468.75
$0.05 10,000.00 $504.35
$0.11 10,000.00 $1,080.75
$0.29 10,000.00 $2,947.50
TOTAL COSTOS FIJOS $1.19
$400.00 POR SERVICIOS$800.00 POR 2 SERVICIOS AL AÑO
$4,000.00 POR SERVICIOS EN 5 AÑOSGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Gasolina)
$11.08
Ah = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIÓN x COEFICIENTE DE CONSUMO (Aceite)
$0.85
TOTAL COSTOS POR CONSUMO $11.93
$41.46TOTAL COSTOS POR OPERACIÓN $41.46
TOTAL COSTO HORARIO $54.58
POR SERVICIOS EN 5 AÑOS
ANALISIS, CALCULO E INTEGRACION DEL % DE INDIRECTOS
GASTO x MES
a) Personal directivo;b) Personal técnico;c) Personal administrativo;
a) Edificios y locales; $15,000.00b) Locales de mantenimiento y guarda;c) Bodegas; $5,000.00d) Instalaciones generales;e) Equipos, muebles y enseres; $1,071.43f) Depreciación o renta, y operación de vehículos, y $2,500.00g) Campamentos;
III. Servicios de los siguientes conceptos:a) Consultores, asesores, servicios y laboratorios, yb) Estudios e investigaciones;
IV. Fletes y acarreos de los siguientes conceptos:a) Campamentos;b) Equipo de construcción;c) Plantas y elementos para instalaciones, yd) Mobiliario;
V. Gastos de oficina de los siguientes conceptos:a) Papelería y útiles de escritorio; $1,500.00
$2,000.00c) Equipo de computación; $3,000.00d) Situación de fondos; $1,500.00e) Copias y duplicados; $500.00f) Luz, gas y otros consumos, y $2,000.00g) Gastos de la licitación pública;
VI. Capacitación y adiestramiento; $10,000.00
VII. Seguridad e higiene; $8,000.00
VIII. Seguros y fianzas, y
IX. Trabajos previos y auxiliares de los siguientes conceptos:a) Construcción y conservación de caminos de acceso;b) Montajes y desmantelamientos de equipo, y
I. Honorarios, sueldos y prestaciones de los siguientes conceptos:
d) Cuota patronal del seguro social y del Instituto del Fondo Nacional de la Vivienda para los Trabajadores;e) Prestaciones a que obliga la Ley Federal del Trabajo para el personal enunciado en los incisos a), b) y c) de esta fracción;f) Pasajes y viáticos del personal enunciado en los incisos a), b) y c) de esta fracción, yg) Los que deriven de la suscripción de contratos de trabajo para el personal enunciado en los incisos a), b) y c) de esta fracción;II. Depreciación, mantenimiento y rentas de los siguientes conceptos:
b) Correo, fax, teléfonos, telégrafos, radio y otros gastos de comunicaciones;
c) Construcción de las siguientes instalaciones generales:1. Campamentos;2. Equipo de construcción, y3. Plantas y elementos para instalaciones.
POR LO GENERAL SE COBRAN EN UN 2 AL MILLAR SOBRE EL MONTO TOTAL DEL CONTRATO
% DE APLICACIÓNNo. DE PERIODOS IMPORTE PORCENTAJE GASTO x MES
$58,500.00 1.65%$31,950.00 0.90%$8,775.00 0.25%
2.80%
10.00% 4.50 $6,750.00 $10,000.00
10.00% 4.50 $2,250.00 $500.00
$250.00
10.00% 4.50 $482.14 $1,690.48
10.00% 4.50 $1,125.00 $2,916.67
$9,000.00
$1,800.00
$350.00
10.00% 4.50 $675.00 $500.00
10.00% 4.50 $900.00 $1,200.00
10.00% 4.50 $1,350.00 $1,500.00
10.00% 4.50 $675.0010.00% 4.50 $225.00 $500.00
10.00% 4.50 $900.00 $1,000.00
$4,500.00
10.00% 4.50 $4,500.00 $2,000.00
10.00% 4.50 $3,600.00 $6,000.00
GASTOS DE ADMINISTRACION DE OFICINA CENTRAL
SUBTOTALES $122,657.14
GASTO TOTAL DE INDIRECTOS = SUBTOTAL GASTOS DE OFICINA CENTRAL + SUBTOTAL GASTOS DE OFICINA DE CAMPO
% DE INDIRECTOS = GASTO TOTAL DE INDIRECTOS / COSTO DIRECTO TOTAL
FIANZA DE CUMPLIMIENTO POR EL 10% DEL MONTO TOTAL DEL CONTRATOFIANZA DE ANTICIPO POR EL 100% DEL IMPORTE DEL ANTICIPO
FIANZA DE CVICIOS OCULTOS POR EL 10% DEL MONTO TOTAL DEL CONTRATO
POR LO GENERAL SE COBRAN EN UN 2 AL MILLAR SOBRE EL MONTO TOTAL DEL CONTRATO
$4,627,137.29
0.002
$9,254.27 x 3 FIANZAS $27,762.82
COSTO DIRECTO TOTAL $3,549,802.42
% DE APLICACIÓN No. DE PERIODOS IMPORTE PORCENTAJE
$216,000.00 6.08%$67,500.00 1.90%
7.99%
100.00% 4.50 $45,000.00
100.00% 4.50 $2,250.00100.00% 4.50 $1,125.00100.00% 4.50 $7,607.14100.00% 4.50 $13,125.00
100.00% 4.50 $40,500.00
100.00% 4.50 $8,100.00
100.00% 4.50 $1,575.00
100.00% 4.50 $2,250.00100.00% 4.50 $5,400.00100.00% 4.50 $6,750.00
100.00% 4.50 $2,250.00100.00% 4.50 $4,500.00100.00% 4.50 $20,250.00
100.00% 4.50 $9,000.00
100.00% 4.50 $27,000.00
$28,168.37
GASTOS DE ADMINISTRACION DE OFICINA DE CAMPO
SUBTOTALES $508,350.51
GASTO TOTAL DE INDIRECTOS = SUBTOTAL GASTOS DE OFICINA CENTRAL + SUBTOTAL GASTOS DE OFICINA DE CAMPO $631,007.66
% DE INDIRECTOS = GASTO TOTAL DE INDIRECTOS / COSTO DIRECTO TOTAL 17.7759%
OFICINA DE CAMPOPERSONAL TECNICOCATEGORIA No. DE SALARIO POR % DE
PERSONAS PERIODO PARTICIPACIONSUPERINTENDENTE 1.00 $30,000.00 100.00%AUX. DE SUPERINTENDENTE 1.00 $18,000.00 100.00%ANALISTA DE COSTOS 0.00 $16,000.00 100.00%
PERSONAL ADMINISTRATIVOCATEGORIA No. DE SALARIO POR % DE
PERSONAS PERIODO PARTICIPACIONCONTADOR 0.00 $8,000.00 100.00%SECRETARIA 0.00 $4,500.00 100.00%ALMACENISTA 1.00 $3,000.00 100.00%CHOFER 1.00 $5,000.00 100.00%VELADOR 1.00 $4,000.00 100.00%AUX. LIMPIEZA 1.00 $3,000.00 100.00%
OFICINA DE CENTRALPERSONAL DIRECTIVOCATEGORIA No. DE SALARIO POR % DE
PERSONAS PERIODO PARTICIPACIONDIRECTOR GENERAL 1.00 $50,000.00 10.00%GERENTE DE CONSTRUCCION 1.00 $40,000.00 10.00%GERENTE DE CONTROL 1.00 $40,000.00 10.00%
PERSONAL TECNICOCATEGORIA No. DE SALARIO POR % DE
PERSONAS PERIODO PARTICIPACIONJEFE DE COSTOS 1.00 $25,000.00 10.00%JEFE DE RECURSOS MATERIALES 1.00 $20,000.00 10.00%ANALISTA DE PRECIOS UNITARIOS 1.00 $16,000.00 10.00%CAPTURISTA DE DATOS 1.00 $10,000.00 10.00%
PERSONAL ADMINISTRATIVOCATEGORIA No. DE SALARIO POR % DE
PERSONAS PERIODO PARTICIPACIONCONTADOR 1.00 $8,000.00 10.00%SECRETARIA 1.00 $4,500.00 10.00%MENSAJERO 1.00 $4,000.00 10.00%AUX. LIMPIEZA 1.00 $3,000.00 10.00%
OBRA 1 $15,000,000.00 33.33%OBRA 2 $25,500,000.00 56.67%
(ESTE PRESUPUESTO) OBRA 3 $4,500,000.00 10.00%
TOTAL $45,000,000.00
No. DE IMPORTEPERIODOS
4.50 $135,000.004.50 $81,000.004.50 $0.00
TOTAL $216,000.00
No. DE IMPORTEPERIODOS
4.50 $0.004.50 $0.004.50 $13,500.004.50 $22,500.004.50 $18,000.004.50 $13,500.00
TOTAL $67,500.00
No. DE IMPORTEPERIODOS
4.50 $22,500.004.50 $18,000.004.50 $18,000.00
TOTAL $58,500.00
No. DE IMPORTEPERIODOS
4.50 $11,250.004.50 $9,000.004.50 $7,200.004.50 $4,500.00
TOTAL $31,950.00
No. DE IMPORTEPERIODOS
4.50 $3,600.004.50 $2,025.004.50 $1,800.004.50 $1,350.00
TOTAL $8,775.00
ANALISIS, CALCULO E INTEGRACION DEL % DE FINANCIAMIENTO
COSTO DIRECTO TOTAL $3,549,802.42 TASA DE INTERES ANUAL% DE INDIRECTOS 17.7759% INDICADOR ECONOMICO ESPECIFICOCOSTO TOTAL DE INDIRECTOS $631,007.66 % DE ANTICIPOCOSTO DIRECTO + INDIRECTOS $4,180,810.07 MONTO DEL ANTICIPOMONTO TOTAL $4,627,137.29 DIAS DE PAGO PARA ESTIMACIONES (ART. 54 LOPSRM)PERIODO DE COBRO DE LA 1RA ESTIMACION 3 TASA DE INTERES APLICABLE AL CALCULO
PERIODO ANTICIPO ESTIMACIONES
$694,070.59 $694,070.59MES 1 $675,897.29MES 2 $1,045,507.17MES 3 $1,303,145.30 $675,897.29 $101,384.59 $574,512.69MES 4 $957,359.24 $1,045,507.17 $156,826.08 $888,681.09MES 5 $645,228.29 $1,303,145.30 $195,471.79 $1,107,673.50
$957,359.24 $143,603.89 $813,755.35$645,228.29 $96,784.24 $548,444.05
TOTALES $4,627,137.29 $694,070.59 $4,627,137.29
% DE FINANCIAMIENTO = INTERES O FINANCIAMIENTO TOTAL / (COSTO DIRECTO + INDIRECTOS)
POR LO TANTO SE APLICA AL PRECIO UNITARIO CON SIGNO INVERSO
OBRA EJECUTADA
AMORTIZACION DEL ANTICIPO
INGRESO O COBRO (Importe
total)
TASA DE INTERES ANUAL 2.80%INDICADOR ECONOMICO ESPECIFICO CETES
15.00%MONTO DEL ANTICIPO $694,070.59DIAS DE PAGO PARA ESTIMACIONES (ART. 54 LOPSRM) 41TASA DE INTERES APLICABLE AL CALCULO 0.3145%
$694,070.59 $694,070.59$610,701.18 ### $83,369.42$944,659.00 ### -$861,289.59 -$2,708.93
$1,177,445.72 ### -$1,464,222.61 -$4,605.28$865,013.70 $23,667.39 -$1,440,555.22 -$4,530.84$582,990.47 $524,683.03 -$915,872.19 -$2,880.61
$813,755.35 -$102,116.84 -$321.18$548,444.05 $446,327.21
$4,180,810.07 -$15,046.84
% DE FINANCIAMIENTO = INTERES O FINANCIAMIENTO TOTAL / (COSTO DIRECTO + INDIRECTOS) -0.3599%
POR LO TANTO SE APLICA AL PRECIO UNITARIO CON SIGNO INVERSO 0.3599%
EGRESO O GASTO
(CD+IND)
DIFERENCIA INGRESO-EGRESO
DIFERENCIA ACUMULADA
INTERES O FINANCIAMIENTO
TOTAL
ANALISIS, CALCULO E INTEGRACION DEL % DE UTILIDADIMPORTE
COSTO DIRECTO $3,549,802.42
INDIRECTOS $631,007.66
FINANCIAMIENTO $15,046.84
SUBTOTAL $4,195,856.91
UTILIDAD PROPUESTA
ISR : IMPUESTP SOBRE LA RENTA
PTU : PARTICIPACION DE LOS TRABAJADORES EN LA UTILIDAD DE LA EMPRESA
UTILIDAD TOTAL EN PORCENTAJE = UTILIDAD PROPUESTA / (1- (ISR+PTU))
IMPORTE DE UTILIDAD TOTAL = % UTILIDAD TOTAL x SUBTOTAL $419,585.69
PORCENTAJE
17.7759%
0.3599%
6.0000%
30.0000% LEY DEL IMPUESTO SOBRE LA RENTA ART. 9
10.0000% ART. 117 LEY FEDERAL DEL TRABAJO
10.0000%
ANALISIS, CALCULO E INTEGRACION DEL % DE CARGOS ADICIONALES
COSTO DIRECTO $3,549,802.42
INDIRECTOS $631,007.66
FINANCIAMIENTO $15,046.84
UTILIDAD $419,585.69
SUBTOTAL $4,615,442.60
Artículo 191. Por el servicio de vigilancia, inspección y control que las leyes de la materiaencomiendan a la Secretaría de la Función Pública, los contratistas con quienes se celebren contratos deobra pública y de servicios relacionados con la misma, pagarán un derecho equivalente al cinco al millarsobre el importe de cada una de las estimaciones de trabajo.
CARGOS ADICIONALES (CA) = ( SUBTOTAL / (1-0.005) ) - SUBTOTALCA = ( $ 4,678,461.98 / (0.995) ) - $ 4,678,461.98 $23,193.18
% DE CARGOS ADICIONALES = CA / SUBTOTAL
ESTE PORCENTAJE DE CARGOS ADICIONALES SOLO APLICA PARA PRESUPUESTOS A PRECIO UNITARIO DE OBRA PUBLICANUNCA PARA PRESUPUESTOS DE PARTICULARES U OBRA PRIVADA
17.78%
0.36%
10.00%
Artículo 191. Por el servicio de vigilancia, inspección y control que las leyes de la materiaencomiendan a la Secretaría de la Función Pública, los contratistas con quienes se celebren contratos deobra pública y de servicios relacionados con la misma, pagarán un derecho equivalente al cinco al millar
0.50%
ESTE PORCENTAJE DE CARGOS ADICIONALES SOLO APLICA PARA PRESUPUESTOS A PRECIO UNITARIO DE OBRA PUBLICANUNCA PARA PRESUPUESTOS DE PARTICULARES U OBRA