  • Essar Power Hazira

    Essar Energy Site Visit

    8th Dec 2011

    T.S. Bhatt

    Head Essar Power Hazira

  • Operating Plants - Overview

    Capacity: 515 MW

    Fuel: Natural gas/Naphtha

    Offtake: Gujarat Electricity Board, Essar

    Steel

    COD: Oct 1997

    Location: Gujarat, India

    Hazira I Bhander

    Capacity: 500 MW

    Fuel: Natural gas

    Offtake: Essar Group companies

    COD: Jan 2006 Oct 2008

    Location: Gujarat, India

    Algoma

    Capacity: 85 MW

    Fuel: Blast furnace gas / Coke oven gas

    Offtake: Ontario Power Authority

    COD: Jun 2009

    Location: Ontario, Canada

    Vadinar

    Capacity: 120 MW

    Fuel: Refinery residue

    Offtake: Essar Oil

    COD: May 2008

    Location: Gujarat, India

    Vadinar P1

    Capacity: 380 MW

    Fuel: Natural Gas

    Offtake: Essar Oil

    Sync: Unit I Oct 2010

    Unit II Jan 2011

    Location: Gujarat, India

  • Our Plants at Hazira, Commissioning Dates

    Capacity: 515 MW Fuel: Natural gas/Naphtha Off take: Gujarat Electricity Board, Essar Steel COD: Oct 1997 Location: Gujarat, India

    Capacity: 500 MW Fuel: Natural gas Off take: Essar Group companies COD: Jan 2006 Oct 2008 Location: Gujarat, India

  • Salient Features

    Plant Configuration

    EPOL- 515 MW

    3 Gas Turbines Generators-3 X 110 MW

    1 Steam Turbine Generator-1 X 185 MW

    BPOL - 500 MW

    3 Gas Turbines 1x100+2x110 MW = 320 MW

    Steam Turbine - I 55 MW = 55 MW

    Steam Turbine- II 125 MW = 125 MW

    Fuel

    NGL/ Naphtha / HSD / Natural Gas

  • COMBINED CYCLE PROCESS

    Air

    Gas

    Turbine Compressor

    Fuel

    Combustion

    System

    Exhaust

    Alternator

    Boiler

    Steam

    Turbine Alternator

    Condenser

    Cooling Water

    Boiler Feed

    Pump

    Condensate

    Extraction Pump

    Deareator To other

    Boilers

    From Other

    Boilers

  • COMBINED CYCLE PROCESS (BPL)

  • 270 MW Power Project ( Hazira 2 )

    Essar Power Hazira Ltd

  • CONFIGURATION :

    Steam Turbines : 2 X 135 MW

    Boilers : 2 X 487 TPH (Multi-Fuel Fired )

    Steam parameters :141bar(a) , 540degC

    Reheater Parameters: 35.1bar(a), 540degC

    FUEL :

    Various combinations of following fuels can be fired :

    Corex Coal, Corex Coal Fines, Corex Coal Dust, Corex Gas,

    Coke Oven Gas & Thermal Coal

    HIGHLIGHTS :

    Generator (Unit 1) Inspection done on 12-Jul-2011

    Steam Turbine testing HP turbine on 30- Nov-2011

    LP turbine by End of Dec-2011

    Boiler Drum (Unit 1) expected at site by Dec 2011

    MULTI-FUEL FIRED POWER PLANT ( HAZIRA 2 )

  • 270 MW PLOT PLAN ( HAZIRA 2 )

  • MAIN EQUIPMENT SUPPLIERS 270 MW

    PACKAGE VENDOR

    STG & Auxiliaries SIEMENS

    Boiler & Auxiliaries BWE

    IDCT SPIG

    CW Pump Jyoti

    Safety Relief Valves Tyco Sanmar

    EBOP ABB

    Generator Transfomers ABB

    Gas Insulated Switchyard ABB

    Emergency DG Set GMMCO

    Plant DCS Honeywell

    Fuel Oil Handling System Thermosystems

    Ash Handling System Mcawber Beekay

  • ENGINEERING PROGRESS - 85%

    DESCRIPTION PROGRESS

    BASIC ENGINEERING 100%

    TECHNICAL SPECIFICATION 95%

    ENGINEERING EESL 70%

    ENGINEERING VENDORS 90%

  • S.N. DESCRIPTION UNIT TOTAL SCOPE COMPLETED % COMPLETION

    1 Piling Nos 4400 3270 77

    2 Concreting Cum 45140 9438 21

    3 Structural Fabrication MT 8262 3813 46

    4 Structural Erection MT 12035 804 6.5

    5 Equipment Erection MT 16244

    6 Piping IM 190952

    7 Cable Laying RM 315000

    OVERALL CONSTRUCTION PROGRESS

  • 2 x487 TPH Multifuel Fired Boilers from M/s BWE

  • Elevation Plan for Boiler

  • 2 nos STEAM TURBINES 2X135MW FROM SIEMENS

  • PROJECT SITE RIGS MOBILIZATION FOR PILING

    CHIMNEY

    AREA

    BOILER-1 BOILER-2

    TG

    BUILDING

    ESP- 2 AREA

    ESP- 1 AREA

  • BOILER -1 & TG BUILDING ERECTION UNDER PROGRESS

    BOILER-1 STRUCTURE

    TG BUILDING STRUCTURE

    TG-1

    DECK TG-2

    DECK

    CHIMNEY

  • STG DECK 1& 2 UNDER CONSTRUCTION

    STG DECK 1 STG DECK 2

    CURRENT

    STATUS

    CURRENT

    STATUS

  • TG DECK & BUILDING VARIOUS STAGES OF CONSTRUCTION

    TG BLDG FOUNDATIONS PILING EXCAVATION TG DECK REINFORCEMENT

    TG DECK CONCRETING TG DECK RAFT COMPLETED TG DECK COLUMNS

  • BOILER FOUNDATIONS AND ERECTION UNDER PROGRESS

    BOILER -1FOUNDATIONS

    BOILER -2FOUNDATIONS

    COAL MILL AND PA

    FOUNDATIONS COMPLETED

  • ESP-1 FOUNDATIONS UNDER PROGRESS

    CURRENT

    STATUS

    ESP-1 FOUNDATIONS AND

    RAFT UNDER PROGRESS

    PILING EXCAVATION

  • ESP-2 FOUNDATIONS UNDER PROGRESS

    CURRENT

    STATUS

    ESP-2 FOUNDATIONS AND

    RAFT UNDER PROGRESS

    PILING EXCAVATION

  • CHIMNEY RAFT CASTING AND REINFORCEMENT

    CURRENT

    STATUS

    ONE QUADRANT OF

    CHIMNEY RAFT CASTING

    COMPLETED

    REINFORCEMENT FOR

    REST OF RAFT UNDER

    PROGRESS

    PILING EXCAVATION & PCC

    REINFORCEMENT

  • COOLING TOWER - PCC & BASIN CONCRETING UNDER

    PROGRESS

    PILING PCC WORK

    BASIN FOUNDATION

    UNDER PROGRESS

    BASIN FOUNDATION

    UNDER PROGRESS

    CURRENT

    STATUS CURRENT

    STATUS

  • TG BUILDING STRUCTURE UNDER FABRICATION

    AT VARIOUS YARDS

  • FABRICATION OF COAL BUNKER UNDER PROGRESS

  • PRESSURE PARTS AND FABRICATED STRUCTURES

  • Plant Performance

    Operating Units

  • Essar Power and Bhander Power

    Year Generation

    (MU)

    Average

    MW

    Export to

    ESTL

    (MU)

    Export to

    GUVNL

    (MU)

    PLF (%)

    2006-07 4714 538 2852.2 1779.0 74.1%

    2007-08 5394 616 3357.1 1946.3 76.8%

    2008-09 4858 555 2979.7 1782.3 59.2%

    2009-10 5086 581 3192.1 1796.8 57.2%

    2010 - 11 5364 612 3778.0 1493.1 60.3%

  • Generation at Hazira

    3188

    2821

    2084 1968

    2975

    2516

    3643

    4228

    4714

    5394

    4858 5086

    5364

    0

    1000

    2000

    3000

    4000

    5000

    6000

    1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

    Gen

    era

    tio

    n (

    MU

    )

    Generation MU

  • 95.6%

    97.0%

    93.5%

    96.9% 97.1%

    94.6%

    98.1%

    96.9%

    97.1%

    94.2%

    96.7%

    97.2%

    98.3% 97.9% 98.5%

    93.5%

    98.9%

    99.8%

    98.5%

    99.6%

    97.3%

    99.7% 99.9% 99.9%

    99.0%

    99.9%

    86.0%

    88.0%

    90.0%

    92.0%

    94.0%

    96.0%

    98.0%

    100.0%

    1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

    Availability % Reliability (%)

    Availability and Reliability

  • Plant Performance

    0.0%

    0.3%

    0.6%

    0.9%

    1.2%

    1.5%

    1.8%

    2.1%

    2.4%

    2.7%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

    Au

    x C

    on

    su

    mp

    tio

    n (

    %)

    PL

    F (

    %)

    PLF % Aux Cons %

  • Highlights

    Essar Power 515 MW:

    Received Integrated Management Systems, PAS:99

    OHSAS 18001:2007 and ISO14001 in January 2009.

    Green Tech Safety Award, 2010 in Gold Category

    Green Tech Environment Award 2010 in Silver Category

    Accident free Days : 3462 Days ( Data up to Nov 2011)

    Bhander Power Limited :

    Received OHSAS:18001 certification in February 2009.

    Green Tech Safety Award, 2010 in Silver Category

    Green Tech Environment Award 2010 in Silver Category

    CII award for Water Efficient Power company 2011

    Accident Free Days : 2492 Days ( Data up to Nov 2011)

  • Highlights

    Shreshtha Suraksha Puraskar for EPOL in 2001 from National Safety Council of India

    Major Overhaul and Other Scheduled Inspections of Gas Turbines and Steam

    Turbines carried out In house at Essar Power Limited and Bhander Power Limited

    Multi fuel Capability with Gas and Naphtha fuels that can be used

    independently, as well as in Mixed mode. Leads to flexibility in case of fuel

    pricing variations, and ensures cost benefit to customer

  • Energy Conservation at EPOL.

    Increase of 3- 4 MW STG Output after replacing Plugs and

    seat lapping of HP Bypass control valves and providing

    isolations.

    STG bearing cooling requirement complied through additional

    cooler . Increased Cooling resulted into stoppage of One ACW

    Pump(55 KW ) and one ACW Booster Pump ( 31 KWH)

    Instrument air system modified to reduce aux power (saving of

    75 kW) and to improve compressor life.

    Clarified water pump impeller trimmed to reduce power

    consumption. Net power saving would be 20 KWH

    Raw water Pump replaced by VFD Motor. Saving potential of

    35 KWH.

    Installation of Wind Spin Fans, in place of Roof Ventilator in

    all Roofs. Wind Spin

    Bypass Control

    Valves

  • Improvements in O&M Design.

    New Installations :

    GTG Inlet Air Cooling System.

    STG IDCT fills height Increase from 3 to 5 . Expected

    STG output gain would be 2.5 MW.

    Provision to receive fuel gas supply from three different

    gas supplier .

    GTG lube oil filtration and dehydration machine

    installed.

    Flux detectors installed on STG generator.

  • Plant Efficiency Improvements

    STG Output increased by 2 MW by minimising the

    hot flue gas leakages in HRSGs.

    Honey Comb seals and Cutter teeth buckets

    installed in Gas turbine for Efficiency improvements.

    Periodical replacement of Gas turbine inlet air filters

    to minimise loss due to high filter Dp.

    Monthly Monitoring of Bypass stack Flue gas

    losses.

    Plant Aux. Consumption considerably reduced due

    to running of Single HPBFP during 2 GT operation.

    Hydro jetting of condensor tubes to remove scale &

    improve the condensor vacuum.

    Reduced Spill over to GUVNL by better Load

    coordination with ESTL.

    Single HPBFP

    during 2 GT

    operation

  • Plant Efficiency Tracking

    On- Line Monitoring of Station Performance. Daily Monitoring of Plant

    Performance related Parameters.

    Daily Monitoring of Equipment Performance.

    Daily Monitoring of Consumables and Water Consumption.

    Periodical GT , Station , Bypass Stack Measurement and Condenser PG

    Tests.

    Regular Water wash of GT based on Performance.

  • Unique Features of Essar Power and Bhander Power

    First IPP Post Liberalization

    Best Safety Practices- Sword of Honor/OHSAS 18001

    Most Environment Friendly with CDM

    Unique Islanding Systems for Grid Support

    Multi fuel with online change over systems

    In-house O&M

    Lowest Man MW Ratio

    High availability and PLF among Similar plants Globally

    Energy Efficient with low Aux consumption and low Heat Rate

    High level of Plant and Business process automation

  • Maintenance Standards

    Maintaining high availability of major equipments Viz. Gas Turbines, Steam turbine and HRSGs

    Over 300 modifications carried out to improve various systems performance

    In house capability to carry out major inspections of gas turbines and steam turbines

    Various modifications done on turbine parts to extend the parts life

    High reliability of Liquid Fuel System by improvements on the Flow divider , Warren Pump seal design, Liquid fuel lines, etc

    Commissioning of inlet air cooling system carried out with in house expertise

  • In House Expertise for inspections

    Major inspection of GTG# 3 carried out in 21 days

    Major Inspection of steam turbine carried out in 22 days simultaneous with

    Gas Turbine Major Inspection

    Developed card repair facility for Mark V and DCS electronic cards.

    In house repair of expensive equipments like Warren pump, Flow divider,

    Dual fuel nozzles, Hydraulic pump, CW Pump

    Relay testing facility developed for testing and calibration of relays

  • Health, Safety and Environment

    Essar Power Hazira

  • SAFETY MEASURES

    Hydrogen sensors in Battery Room.

    Naphtha Detectors in Gas Turbine Compt.

    Monsoon preparedness improved.

    Behaviour Based Safety on Stream.

    Auto HVWS system at Station Transformers.

    OHSAS 18001 Certified

    HIGH RISK JOBS

    DONE SAFELY

  • Environmental Management

    ESSAR POWER LIMITED received Integrated

    Management Systems, PAS:99 Certification for

    OHSAS 18001:2007 and ISO14001

    Uses clean fuel, natural gas with very low emissions level .

    Green belt developed all around the plant with planting of over one lakh trees.

    Water systems modified to optimize the water requirements.

    Chlorine Dioxide System introduced in Nov 2005 COC improved from 5 to 5.5.

    Cooling Water blow down used for Cooling purpose in HBI plant and gardening in township. Treated

    effluent water used for horticulture.

    Control room - back up alarm system, made paperless.

  • Environment - Consents & Ambient Air Quality

    Consents for Essar Power.

    1. Air

    2. Water

    3. Waste Hazard .

    Consents are valid till 24.06.2014

    Month SPM (PPM) (500) SO2 (PPM) (120) NOX (PPM) (120)

    Sep-07 211 7.9 34.4

    Oct-07 143 7.6 32.8

    Nov-07 253 7.2 31.1

    Dec-07 272 8 32.1

    Jan-08 216 8.1 32.7

  • Water Conservation at EPOL

    Water Saving

    Condenser cooling 5200 m3/day

    Filter Back wash 168 m3/day

    Salt Recovery water 90 m3/day

    Treated effluent used

    for gardening 500 m3/day

    Total Saving 5758 m3/day

    Savings @ Rs. 25900 / day @Rs. 12/m3

    Annual Rs.335 Lakh

  • Reliability Improvements.

    DD 1 & 3 hydraulic system accumulators.

    Naphtha settling & Inter tank Filtration Scheme introduced to ensure clean

    Naphtha without filterable particles for the gas turbines.

    Significant improvements on the reliability of Liquid Fuel System by

    improvements on the Flow divider , Warren Pump seal design etc.

    Accumulator for GTGs Naphtha forwarding system.

    Auto islanding scheme for station with stable load.

    New common header for GT ACW IDCT.

    GTG Misc MCC- DC supply 110 V DC instead of 110V AC

    6.6 KV Station switchgear auto-changeover scheme.

  • HR Development Practices

    12 Engineers sent to G.E, USA for Systems training

    Simulator operation training a regular feature

    Regular O&M training from leading suppliers

    HR Development through in-house and external Management Programs

    Job Rotation within functions and lateral transfers for wider exposure

    Employees exposed to seminars & workshops related to Power industry

  • Manpower to MW Ratio

    National Standard -Thermal 2.75

    Best - Coal based 1.50

    Gas Based average 0.43

    Essar Power Ltd. 0.11

  • Awards and Achievements

    Essar Power Hazira

  • Certifications and Accolades

    51

    Green tech award

    Gold and silver award

    BSI Management System

    ISO14001 & PAS 99

    BSI Management System

    OHSAS 18001

    Gujarat Safety Council

    Certificate of Appreciation

    Gujarat Safety Council

    Certificate of Appreciation

    National Safety Council

    Shreshtha Surksha Puraskar

    BSC - National Safety Award

    GSC - Certificate of Appreciation

    BSC - Five star rating & Sword of honour

    GSC - Certificate of Appreciation

    National Safety Council

    Yogyata Praman patra

    Essar Power 100% operational

    DNV - ISRS Level III

    1997 1998 1999 2000 2001 2005 2006 2007 2008 2009 2010

    BPL receives CII "Most Water Efficient Unit" award November 2011

    Greentech Foundation Silver award for Environment Excellence 2011 EPOL & BPL

    BSI Management System BPL - ISO14001 & PAS 99

    Greentech

    Gold and silver award

    BSI Management System

    EPOL - ISO14001 & PAS 99

    BSI Management System

    OHSAS 18001

    Gujarat Safety Council

    Certificate of Appreciation

    Gujarat Safety Council

    Certificate of Appreciation

    National Safety Council

    Shreshtha Surksha Puraskar

    BSC - National Safety Award

    GSC - Certificate of Appreciation

    BSC - Five star rating & Sword of honour

    GSC - Certificate of Appreciation

    National Safety Council

    Yogyata Praman patra

    Essar Power 100% operational

    DNV - ISRS Level III

    1997 1998 1999 2000 2001 2005 2006 2007 2008 2009 2010 2011