OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014
Transcript
Page 1: OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014.

OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO

2014

Page 2: OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014.

VALOR APROXIMADO $157.502.263.15, PLAZO DE ENTREGA 4 MESES , AVANCE DE OBRA 85 % .FECHA DE ENTREGA EL 20 DE MAYO DE 2014

CONSTRUCCION BATERIA DE BAÑOS PARA LA I.E. MAGDALENA

Page 3: OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014.
Page 4: OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014.
Page 5: OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014.

CONSTRUCCION DE MURO DE CERRAMIENTO EN LA I.E INSEANDES

VALOR $ 52.259.000 APROX , AVANCE DE OBRA 20 % PARA ENTREGAR TERMINADO EN UN MES .CONSTA DE COLUMNAS , VIGAS , MURO EN LADRILLO, CIMENTACION CICLOPEA Y VIGA DE AMARRE (CONTRAPESOS)

Page 6: OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014.
Page 7: OBRAS PARA EL MEJORAMIENTO DE LA INFRAESTRUCTURA EDUCATIVA EN SOGAMOSO 2014.

CONSTRUCCIÓN MURO EN TIERRA ARMADA Y TERMINACIÓN CERRAMIENTO EN MALLA

ESLABONADA I.E NUESTRA SEÑORA MORCACONSTRUCCIÓN MURO EN TIERRA ARMADA Y TERMINACIÓN CERRAMIENTO EN MALLA ESLABONADA I.E NUESTRA SEÑORA MORCA, AVANCE DE OBRA 55% FECHA DE TERMINACIÓN EN 25 DÍAS .VALOR INICIAL APROXIMADO $ 139.000.000.00