Obra
Sub Presupuesto
Cliente
Ubicación
ITEM DESCRIPCION UNIDAD METRADO
01 VEREDAS
01.01 OBRAS PRELIMINARES
01.01.01 TRAZO Y REPLANTEO m2 66.20
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA VEREDAS, H=10CM m2 66.20
01.02.02 PERFILADO Y COMPACTADO DE VEREDAS m2 66.20
01.03 CONCRETO SIMPLE
01.03.01 ENCOFRADO Y DESENCOFRADO P/VEREDAS m2 75.45
01.03.02 VEREDA RIGIDA DE CONCRETO F'C=175 KG/CM2 E=10CM.,PASTA 1:2 m2 66.20
01.03.03 JUNTAS DE DILATACIÓN EN VEREDAS m2 37.40
02 PAVIMENTO RIGIDO
02.01 MOVIMIENTO DE TIERRAS
02.01.01 RELLENO CON MATERIAL DE PRESTAMO EN BASE DE PAVIMENTO m3 23.95
02.02 CONCRETO F´C 210 KG/CM2
02.02.01 CONCRETO FC 210 KG/CM2 PAVIMENTO RIGIDO m3 23.95
02.03 CANAL DE CONCRETO ARMADA
02.03.01 COLOCACION DE TAPAS DE FF - INSPECCION und 3.00
Obra REAHBILITACION DEL SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DEL PASAJE LA OROYA - MARIANO MELGAR
Sub Presupuesto SARDINEL TIPO BURBUJA, REDUCCION 20 cm BERMA
Cliente MINUCIPALIDAD DISTRITAL DE MARIANO MELGAR
Ubicación MARIANO MELGAR - AREQUIPA - AREQUIPA
ITEM DESCRIPCION UNIDAD METRADO
01 BERMAS
01.01 OBRAS PRELIMINARES
01.01.01 TRAZO Y REPLANTEO m2 66.20
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA VEREDAS, H=10CM m2 66.20
01.02.02 PERFILADO Y COMPACTADO DE VEREDAS m2 66.20
01.03 CONCRETO SIMPLE
01.03.01 BERMA RIGIDA DE CONCRETO F'C=175 KG/CM2 E=10CM.,PASTA 1:2 m2 66.20
02 SARDINEL TIPO BURBUJA
02.01 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACION DE ESTRUCTURAS m 349.37
02.01.02 ELIMINACION DE MATERIAL CON EQUIPO m3 16.77
02.02 CONCRETO SIMPLE
02.02.01 SARDINEL SUMERGIDO TIPO BURBUJA INV ENCOFRADO DE F'c = 175 Kg/cm2 m 349.37
02.03 OTROS
02.03.01 JUNTAS DE DILATACIÓN C/3M (UND) und 114.00
02.03.02 PINTURA EN SARDINELES TIPO BURBUJA m 349.37
ITEM DESCRIPCION UNIDAD P.U.
01 VEREDAS
01.01 OBRAS PRELIMINARES
01.01.01 TRAZO Y REPLANTEO m2 1.65
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA VEREDAS, H=10CM m2 6.89
01.02.02 PERFILADO Y COMPACTADO DE VEREDAS m2 6.88
01.03 CONCRETO SIMPLE
01.03.01 ENCOFRADO Y DESENCOFRADO P/VEREDAS m2 37.35
01.03.02 VEREDA RIGIDA DE CONCRETO F'C=175 KG/CM2 E=10CM.,PASTA 1:2 m2 41.75
01.03.03 JUNTAS DE DILATACIÓN EN VEREDAS m2 5.73
PRESUPUESTO ADICIONAL N° 01
REAHBILITACION DEL SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DEL PASAJE LA OROYA - MARIANO MELGAR
20 CM DE VEDERA ADICIONAL, PAVIMENTO, TAPAS DE INSPECCION
MINUCIPALIDAD DISTRITAL DE MARIANO MELGAR
MARIANO MELGAR - AREQUIPA - AREQUIPA
CUADRO COMPARATIVO ADICIONAL Y DEDUCTIVO VINCULANTE
COSTO DIRECTO
GASTOS GENERALES
COSTO DIRECTO
GASTOS GENERALES
TOTAL PRESUPUESTO
TOTAL PRESUPUESTO
PRESUPUESTO DEDUCTIVO N° 01
02 PAVIMENTO RIGIDO
02.01 MOVIMIENTO DE TIERRAS
02.01.01 RELLENO CON MATERIAL DE PRESTAMO EN BASE DE PAVIMENTO m3 58.05
02.02 CONCRETO F´C 210 KG/CM2
02.02.01 CONCRETO FC 210 KG/CM2 PAVIMENTO RIGIDO m3 374.67
02.03 CANAL DE CONCRETO ARMADA
02.03.01 COLOCACION DE TAPAS DE FF - INSPECCION und 215.05
03 BERMAS
03.01 OBRAS PRELIMINARES
03.01.01 TRAZO Y REPLANTEO m2 1.65
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA VEREDAS, H=10CM m2 7.18
03.02.02 PERFILADO Y COMPACTADO DE VEREDAS m2 21.50
03.03 CONCRETO SIMPLE
03.03.01 BERMA RIGIDA DE CONCRETO F'C=175 KG/CM2 E=10CM.,PASTA 1:2 m2 34.78
04 SARDINEL TIPO BURBUJA
04.01 MOVIMIENTO DE TIERRAS
04.01.01 EXCAVACION DE ESTRUCTURAS m 1.57
04.01.02 ELIMINACION DE MATERIAL CON EQUIPO m3 19.41
04.02 CONCRETO SIMPLE
04.02.01 SARDINEL SUMERGIDO TIPO BURBUJA INV ENCOFRADO DE F'c = 175 Kg/cm2 m 19.16
04.03 OTROS
04.03.01 JUNTAS DE DILATACIÓN C/3M (UND) und 5.58
04.03.02 PINTURA EN SARDINELES TIPO BURBUJA m 4.41
TOTAL PRESUPUESTO
COSTO DIRECTO
GASTOS GENERALES
PRECIO PARCIAL
1.65 109.23
6.89 456.12
6.88 455.46
37.35 2,818.06
41.75 2,763.85
5.73 214.30
58.05 1,390.30
374.67 8,973.35
215.05 645.15
17,825.81
891.29
18,717.10
REAHBILITACION DEL SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DEL PASAJE LA OROYA - MARIANO MELGAR
PRECIO PARCIAL
1.65 109.23
7.18 475.32
21.50 1,423.30
34.78 2,302.44
1.57 548.51
19.41 325.51
19.16 6,693.93
5.58 636.12
4.41 1,540.72
14,055.07
702.75
14,757.82
66.20 109.23 109.23
66.20 456.12 456.12
66.20 455.46 455.46
75.45 - -
66.20 2,763.85 2,763.85
37.40 214.30 214.30
PRESUPUESTO ADICIONAL N° 01
REAHBILITACION DEL SERVICIO DE TRANSITABILIDAD PEATONAL Y VEHICULAR DEL PASAJE LA OROYA - MARIANO MELGAR
20 CM DE VEDERA ADICIONAL, PAVIMENTO, TAPAS DE INSPECCION
MINUCIPALIDAD DISTRITAL DE MARIANO MELGAR
MARIANO MELGAR - AREQUIPA - AREQUIPA
PARCIAL
PARCIAL
CUADRO COMPARATIVO ADICIONAL Y DEDUCTIVO VINCULANTE
COSTO DIRECTO
GASTOS GENERALES
COSTO DIRECTO
GASTOS GENERALES
TOTAL PRESUPUESTO
TOTAL PRESUPUESTO
PRESUPUESTO DEDUCTIVO N° 01
METRADOS
ADICIONAL
DEDUCTIVO
VINCULANTE ADICIONAL DEDUCTIVO
153.86
23.95 1,390.30 1,390.30
23.95 8,973.35 8,973.35
3.00 645.15 645.15
66.20 -109.23 -109.23
66.20 -475.32 -475.32
66.20 -1,423.30 -1,423.30
66.20 -2,302.44 -2,302.44
349.37 -548.51 -548.51
16.77 -325.51 -325.51
349.37 -6,693.93 -6,693.93
114.00 -636.12 -636.12
349.37 -1,540.72 -1,540.72
952.68
47.63
1,000.31 TOTAL PRESUPUESTO
COSTO DIRECTO
GASTOS GENERALES
METRADOS
ITEM DESCRIPCION
01 VEREDAS
01.01 OBRAS PRELIMINARES
01.01.01 TRAZO Y REPLANTEO
CANT. LONGITUD ANCHO
(MT) (MT)
CUADRA 01 - AREA = -
- AREA = -
1.00 AREA = 1.94
CUADRA 02 1.00 AREA =
1.00 AREA = 12.08
CUADRA 03 1.00 AREA = 10.31
- AREA = -
CALLE ROSASPATA 1.00 AREA = 11.12
- AREA = -
CUADRA 04 - AREA = -
01.01.03 MOVIMIENTO DE TIERRAS
CANT. LONGITUD ANCHO
(MT) (MT)
CUADRA 01 - AREA = -
- AREA = -
1.00 AREA = 1.94
CUADRA 02 1.00 AREA =
1.00 AREA = 12.08
CALLES/PASAJES
LADO IZQUIERDO A1
CALLES/PASAJES
LADO IZQUIERDO A1
AREA VEREDAS
CUADRA 03 1.00 AREA = 10.31
1.00 AREA = -
CALLE ROSASPATA 1.00 AREA = 11.12
- AREA = -
CUADRA 04 - AREA = -
01.01.03.02 PERFILADO Y COMPACTADO DE VEREDAS
CANT. LONGITUD ANCHO
(MT) (MT)
CUADRA 01 - AREA = -
- AREA = -
1.00 AREA = 1.94
CUADRA 02 1.00 AREA =
1.00 AREA = 12.08
CUADRA 03 1.00 AREA = 10.31
1.00 AREA = -
CALLE ROSASPATA 1.00 AREA = 11.12
- AREA = -
CUADRA 04 - AREA = -
CONCRETO SIMPLE
VEREDAS
ENCOFRADO Y DESENCOFRADO P/VEREDAS
CALLES/PASAJES
CANT.
CUADRA 01
AREA VEREDAS
AREA VEREDAS
CALLES/PASAJES
LADO IZQUIERDO A1
CUADRA 02
CUADRA 03
CALLE ROSASPATA
CUADRA 04
01.01.04.01.02 VEREDA RIGIDA DE CONCRETO F'C=175 KG/CM2 E=10CM.,PASTA 1:2
CANT. LONGITUD ANCHO
(MT) (MT)
CUADRA 01 - AREA = -
- AREA = -
1.00 AREA = 1.94
CUADRA 02 1.00 AREA =
1.00 AREA = 12.08
CUADRA 03 1.00 AREA = 10.31
1.00 AREA = -
CALLE ROSASPATA 1.00 AREA = 11.12
- AREA = -
CUADRA 04 - AREA = -
01.01.04.01.03 JUNTAS DE DILATACIÓN EN VEREDAS
CALLES/PASAJES IZQ IZQ. L. JUNTA
AREA VEREDAS
TOTAL (m2)
CALLES/PASAJES
LADO IZQUIERDO A1
LONGITUD CANT. ASFALTICA
L
CUADRA 01 8.88 3.00 0.20
16.43 6.00 0.20
17.12 6.00 0.20
8.02 3.00 0.20
CUADRA 02 27.67 9.00 0.20
7.60 3.00 0.20
0.52 1.00 0.20
18.05 6.00 0.20
CUADRA 03 12.26 4.00 0.20
21.87 7.00 0.20
31.28 10.00 0.20
CALLE ROSASPATA 29.22 10.00 0.20
19.84 7.00 0.20
CUADRA 04 8.45 3.00 0.20
19.92 7.00 0.20
29.86 10.00 0.20
TOTAL (m)
02.06
02.06.01 RELLENO CON MATERIAL DE PRESTAMO EN BASE DE PAVIMENTO
CUADRA 05 - Area - -
- Area - -
CUADRA 04 1.00 Area 52.95 0.20
1.00 Area 16.13 0.20
CUADRA 03 1.00 Area -
1.00 Area -
CUADRA 02 1.00 Area 22.99 0.20
1.00 Area 27.70 0.20
CUADRA 01 1.00 Area -
1.00 Area -
1.00 Area -
1.00 Area -
PAVIMENTO RIGIDO DE CONCRETO
LONGITUD ANCHO TOTAL
(MT) (MT) A1 + A2
AREA = - -
AREA = - -
AREA = 0.43 2.37
AREA = 9.03 9.03
AREA = 2.65 14.73
AREA = 13.98 24.29
AREA = -
AREA = 4.66 15.78
AREA = - - EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA VEREDAS, H=10CM
AREA = - - CANT.
CUADRA 01 -
-
1.00
CUADRA 02 1.00
LONGITUD ANCHO TOTAL 1.00
(MT) (MT) A1 + A2
CUADRA 03 1.00
1.00
AREA = - -
AREA = - - CALLE ROSASPATA 1.00
AREA = 0.43 2.37 -
AREA = 9.03 9.03 CUADRA 04 -
AREA = 2.65 14.73
CALLES/PASAJES
AREA VEREDAS
LADO DERECHO A2
LADO DERECHO A2
AREA VEREDAS 66.20
AREA = 13.98 24.29
AREA = -
AREA = 4.66 15.78
AREA = - -
AREA = - -
LONGITUD ANCHO TOTAL
(MT) (MT) A1 + A2
AREA = - -
AREA = - -
AREA = 0.43 2.37
AREA = 9.03 9.03
AREA = 2.65 14.73
AREA = 13.98 24.29
AREA = -
AREA = 4.66 15.78
AREA = - -
AREA = - -
LADO IZQUIERDO A1= L x aLADO DERECHO A2= L x a AREA =
A1+A2
LONGITUD ALTO LONGITUD ALTO
(MT) (MT) (MT) (MT)
408.00 0.10 5.15 0.10 41.32
8.02 0.10 11.18 0.10 1.92
- 0.10 -
- 0.10 -
AREA VEREDAS
AREA VEREDAS 66.20
AREA VEREDAS 66.20
LADO DERECHO A2
27.67 0.10 14.75 0.10 4.24
7.60 0.10 5.79 0.10 1.34
0.52 0.10 22.23 0.10 2.28
18.05 0.10 13.23 0.10 3.13
12.26 0.10 5.42 0.10 1.77
21.87 0.10 23.76 0.10 4.56
31.28 0.10 13.49 0.10 4.48
9.53 0.10 0.95
18.01 0.10 1.80
29.22 0.10 21.22 0.10 5.04
19.84 0.10 6.44 0.10 2.63
- 0.10 - 0.10 -
- 0.10 - 0.10 -
- 0.10 - 0.10 -
75.45
LONGITUD ANCHO TOTAL
(MT) (MT) A1 + A2
AREA = - -
AREA = - -
AREA = 0.43 2.37
AREA = 9.03 9.03
AREA = 2.65 14.73
AREA = 13.98 24.29
AREA = -
AREA = 4.66 15.78
AREA = - -
AREA = - -
DER DER. L. JUNTA TOTAL
AREA VEREDAS 66.20
TOTAL (m2)
LADO DERECHO A2
LONGITUD CANT. ASFALTICA LI + LD
L
35.62 12.00 0.20 3.00
11.18 4.00 0.20 2.00
1.20
0.60
14.75 5.00 0.20 2.80
5.79 2.00 0.20 1.00
22.23 8.00 0.20 1.80
13.23 5.00 0.20 2.20
5.42 2.00 0.20 1.20
23.76 8.00 0.20 3.00
13.49 5.00 0.20 3.00
9.53 3.00 0.20 0.60
18.01 6.00 0.20 1.20
21.22 7.00 0.20 3.40
6.44 2.00 0.20 1.80
33.83 11.00 0.20 2.80
29.81 10.00 0.20 3.40
6.72 2.00 0.20 2.40
RELLENO CON MATERIAL DE PRESTAMO EN BASE DE PAVIMENTO 23.95 m3
-
-
10.59 POR ANCHO DE CALZADA
3.23
-
-
4.60 POR TUBERIA
5.54
-
-
-
-
37.40
EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA VEREDAS, H=10CM 66.20
LONGITUD ANCHO LONGITUD ANCHO TOTAL
(MT) (MT) (MT) (MT) A1 + A2
AREA = - AREA = - -
AREA = - AREA = - -
AREA = 1.94 AREA = 0.43 2.37
AREA = AREA = 9.03 9.03
AREA = 12.08 AREA = 2.65 14.73
AREA = 10.31 AREA = 13.98 24.29
AREA = - AREA = -
AREA = 11.12 AREA = 4.66 15.78
AREA = - AREA = - -
AREA = - AREA = - -
66.20
LADO IZQUIERDO A1 LADO DERECHO A2
AREA VEREDAS
66.20 AREA VEREDAS
BERMAS
OBRAS PRELIMINARES
TRAZO Y REPLANTEO
CANT. LONGITUD ANCHO LONGITUD ANCHO
(MT) (MT) (MT) (MT)
CUADRA 01
CUADRA 02 - AREA = - AREA = -
- AREA = - AREA = -
1.00 AREA = 1.94 AREA = 0.43
CUADRA 03 1.00 AREA = AREA = 9.03
1.00 AREA = 12.08 AREA = 2.65
1.00 AREA = 10.31 AREA = 13.98
1.00 AREA = - AREA =
CALLE ROSASPATA 1.00 AREA = 11.12 AREA = 4.66
- AREA = - AREA = -
- AREA = - AREA = -
MOVIMIENTO DE TIERRAS
EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA VEREDAS, H=10CM
CALLES/PASAJES LADO IZQUIERDO A1 LADO DERECHO A2
CANT. LONGITUD ANCHO LONGITUD ANCHO
(MT) (MT) (MT) (MT)
CUADRA 01 - AREA = - AREA = -
- AREA = - AREA = -
1.00 AREA = 1.94 AREA = 0.43
CUADRA 02 1.00 AREA = AREA = 9.03
1.00 AREA = 12.08 AREA = 2.65
CUADRA 03 1.00 AREA = 10.31 AREA = 13.98
1.00 AREA = - AREA =
CALLE ROSASPATA 1.00 AREA = 11.12 AREA = 4.66
- AREA = - AREA = -
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
TOTAL M2
CUADRA 04 - AREA = - AREA = -
AREA VEREDAS
MOVIMIENTO DE TIERRAS
PERFILADO Y COMPACTADO DE VEREDAS
CANT. LONGITUD ANCHO LONGITUD ANCHO
(MT) (MT) (MT) (MT)
CUADRA 01 - AREA = - AREA = -
- AREA = - AREA = -
1.00 AREA = 1.94 AREA = 0.43
CUADRA 02 1.00 AREA = AREA = 9.03
1.00 AREA = 12.08 AREA = 2.65
CUADRA 03 1.00 AREA = 10.31 AREA = 13.98
1.00 AREA = - AREA =
CALLE ROSASPATA 1.00 AREA = 11.12 AREA = 4.66
- AREA = - AREA = -
CUADRA 04 - AREA = - AREA = -
EXTENDIDO Y COMPACTADO DE BASE GRANULAR PARA BERMAS, H=10CM
CANT. LONGITUD ANCHO LONGITUD ANCHO
(MT) (MT) (MT) (MT)
CUADRA 01 - AREA = - AREA = -
- AREA = - AREA = -
1.00 AREA = 1.94 AREA = 0.43
CUADRA 02 1.00 AREA = AREA = 9.03
1.00 AREA = 12.08 AREA = 2.65
CUADRA 03 1.00 AREA = 10.31 AREA = 13.98
1.00 AREA = - AREA =
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
AREA VEREDAS
CALLE ROSASPATA 1.00 AREA = 11.12 AREA = 4.66
- AREA = - AREA = -
CUADRA 04 - AREA = - AREA = -
CONCRETO SIMPLE
BERMA RIGIDA DE CONCRETO F'C=175 KG/CM2 E=10CM.,PASTA 1:2
CANT. LONGITUD ANCHO LONGITUD ANCHO
(MT) (MT) (MT) (MT)
CUADRA 01 - AREA = - AREA = -
1.00 AREA = 1.94 AREA = 0.43
CUADRA 02 1.00 AREA = - AREA = -
1.00 AREA = - AREA = 9.03
1.00 AREA = 12.08 AREA = 2.65
CUADRA 03 1.00 AREA = 10.31 AREA = 13.98
1.00 AREA = AREA = -
2.00 AREA = -
1.00 AREA = -
CALLE ROSASPATA 1.00 AREA = 11.12 AREA = 4.66
1.00 AREA = - AREA = -
01.03.02 SARDINEL TIPO BURBUJA
01.03.02.01 MOVIMIENTO DE TIERRAS
01.03.02.01.01 EXCAVACION DE ESTRUCTURAS
CANT. LONGITUD ANCHO LONGITUD
(MT) (MT) (MT)
CUADRA 01 1.00 4.09 5.16
1.00 13.19 15.16
CUADRA 02 1.00 27.66 14.74
1.00 8.23 22.27
1.00 18.37 0.81
AREA VEREDAS
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
AREA VEREDAS
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
13.23
CUADRA 03 1.00 63.51 20.67
1.00 18.32
1.00 3.93
1.00 3.93
1.00 15.25
CALLE ROSASPATA 1.00 15.64 5.53
1.00 27.53 17.80
14.35
01.03.02.01.02 ELIMINACION DE MATERIAL CON EQUIPO
PROVENIENTE DE VOLUMEN ESPONJAMIENTOVOLUMEN
(CORTE - RELLENO) (%) (MT3)
Excavacion manual a nivel de subrasante
13.97 1.20 16.77
TOTAL (m3) 16.77
01.03.02.02 CONCRETO SIMPLE
01.03.02.02.01 SARDINEL SUMERGIDO TIPO BURBUJA INV ENCOFRADO DE F'c = 175 Kg/cm2
CANT. LONGITUD ANCHO LONGITUD
(MT) (MT) (MT)
CUADRA 01 1.00 4.09 5.16
1.00 13.19 15.16
CUADRA 02 1.00 27.66 14.74
1.00 8.23 22.27
1.00 18.37 0.81
13.23
CUADRA 03 1.00 63.51 20.67
1.00 18.32
TOTAL M
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
1.00 3.93
1.00 3.93
1.00 15.25
CALLE ROSASPATA 1.00 15.64 5.53
1.00 27.53 17.80
14.35
01.03.02.02.02 JUNTAS DE DILATACIÓN C/3M (UND)
CANT. LONGITUD JUNTAS LONGITUD
(MT) (UND) (MT)
CUADRA 01 1.00 4.09 1.00 5.16
1.00 13.19 4.00 15.16
CUADRA 02 1.00 27.66 9.00 14.74
1.00 8.23 3.00 22.27
1.00 18.37 6.00 0.81
13.23
CUADRA 03 1.00 63.51 21.00 20.67
1.00 18.32
1.00 3.93
1.00 3.93
1.00 15.25
CALLE ROSASPATA 1.00 15.64 5.00 5.53
1.00 27.53 9.00 17.80
14.35
01.03.02.02.03 PINTURA EN SARDINELES TIPO BURBUJA
CANT. LONGITUD ANCHO LONGITUD
(MT) (MT) (MT)
TOTAL M
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
UND
CALLES/PASAJES
LADO IZQUIERDO A1 LADO DERECHO A2
CUADRA 01 1.00 4.09 5.16
1.00 13.19 15.16
CUADRA 02 1.00 27.66 14.74
1.00 8.23 22.27
1.00 18.37 0.81
13.23
CUADRA 03 1.00 63.51 20.67
1.00 18.32
1.00 3.93
1.00 3.93
1.00 15.25
CALLE ROSASPATA 1.00 15.64 5.53
1.00 27.53 17.80
14.35
TOTAL M
66.20
TOTAL
A1 + A2
-
-
2.37
9.03
14.73
24.29
-
15.78
-
-
66.20
TOTAL
A1 + A2
-
-
2.37
9.03
14.73
24.29
-
15.78
-
66.20
-
66.20
TOTAL
A1 + A2
-
-
2.37
9.03
14.73
24.29
-
15.78
-
-
TOTAL
A1 + A2
-
-
2.37
9.03
14.73
24.29
-
66.20
15.78
-
-
66.20
TOTAL
A1 + A2
-
2.37
-
-
9.03
14.73
24.29
-
-
-
15.78
-
349.37 m
ANCHO TOTAL
(MT) L1 + L2
9.25
28.35
42.40
30.50
19.18
66.20
66.20
LADO DERECHO A2
13.23
84.18
18.32
3.93
3.93
15.25
21.17
45.33
14.35
16.77 m3
SARDINEL SUMERGIDO TIPO BURBUJA INV ENCOFRADO DE F'c = 175 Kg/cm2 349.37 m
ANCHO TOTAL
(MT) A1 + A2
9.25
28.35
42.40
30.50
19.18
13.23
84.18
18.32
TOTAL M 349.37
LADO DERECHO A2
3.93
3.93
15.25
21.17
45.33
14.35
114.00 und
JUNTAS TOTAL
(UND) A1 + A2
2.00 3.00
5.00 9.00
5.00 14.00
7.00 10.00
- 6.00
4.00 4.00
7.00 28.00
6.00 6.00
1.00 1.00
1.00 1.00
5.00 5.00
2.00 7.00
6.00 15.00
5.00 5.00
349.37 m
ANCHO TOTAL
(MT) A1 + A2
TOTAL M 349.37
LADO DERECHO A2
UND 114.00
LADO DERECHO A2
9.25
28.35
42.40
30.50
19.18
13.23
84.18
18.32
3.93
3.93
15.25
21.17
45.33
14.35
TOTAL M 349.37